πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

Grid infrastructure β€Ί Connection queue β€Ί Solar + storage

SOLAR + STORAGE Β· NGET

Flash Solar Farm

Flash Solar Farm is a 800 MW solar + storage project consented, connecting to the National Grid (England & Wales) network at Staythorpe 400kV Substation, with capacity due from May 2028. The connection agreement is held by Elements Green Trent Ltd.

Project stageConsented
  1. Planning (completed)
  2. Consented (current stage)
  3. Construction (not yet reached)
  4. OperatingFrom May 2028 (not yet reached)
  5. Closed (not yet reached)

Connection details

NESO project number
PRO-001634-2
Customer
Elements Green Trent Ltd
Technology
Energy Storage System, PV Array (Photo Voltaic/solar)
Total capacity
800 MW
Change in this agreement
+440 MW
Capacity effective from
1 May 2028
Connection site
Staythorpe 400kV Substation
Transmission owner
National Grid (England & Wales)
Connection type
Direct connection to the transmission network
NESO project status
Consents Approved

Connection site

The marker shows the connection substation, not the project itself, with the transmission network around it.

Projects connecting near Staythorpe Β· Grid map

Other projects at Staythorpe 400kV Substation

Source: NESO Transmission Entry Capacity (TEC) register, downloaded 8 November 2026. Contains data from NESO, licensed under the NESO Open Data Licence. Report a problem