Grid infrastructure › Connection queue › Solar + storage

SOLAR + STORAGE · NGET

Bradenham - Thetford (Necton) GEC (Ethos Green)

Bradenham - Thetford (Necton) GEC (Ethos Green) is a 850 MW solar + storage project in planning, connecting to the National Grid (England & Wales) network at Necton 400kV Substation, with capacity due from October 2033. The connection agreement is held by Necton Green Energy Centre Ltd.

Project stageIn planning
  1. Planning (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingFrom Oct 2033 (not yet reached)
  5. Closed (not yet reached)

Scoping and awaiting consents are both shown as planning. A connection agreement does not mean the project will be built: many queue projects never reach construction.

Connection details

NESO project number
PRO-004346
Customer
Necton Green Energy Centre Ltd
Technology
Demand, Energy Storage System, PV Array (Photo Voltaic/solar), Reactive Compensation
Total capacity
850 MW
Change in this agreement
+850 MW
Capacity effective from
1 October 2033
Connection site
Necton 400kV Substation
Transmission owner
National Grid (England & Wales)
Connection type
Direct connection to the transmission network
NESO project status
Scoping
Connections reform gate
Gate 1

Connection site

The marker shows the connection substation, not the project itself, with the transmission network around it.

Projects connecting near Necton · Grid map

Other projects at Necton 400kV Substation

Source: NESO Transmission Entry Capacity (TEC) register, downloaded 8 November 2026. Contains data from NESO, licensed under the NESO Open Data Licence. Report a problem