Grid infrastructure › Connection queue › Battery storage

BATTERY STORAGE · NGET

Necton Greener Grid Park

Necton Greener Grid Park is a 0 MW battery storage project consented, connecting to the National Grid (England & Wales) network at Necton 400kV Substation, with capacity due from October 2026. The connection agreement is held by Necton Grid Solutions Limited.

Project stageConsented
  1. Planning (completed)
  2. Consented (current stage)
  3. Construction (not yet reached)
  4. OperatingFrom Oct 2026 (not yet reached)
  5. Closed (not yet reached)

Connection details

NESO project number
PRO-002562-1
Customer
Necton Grid Solutions Limited
Technology
Energy Storage System, Reactive Compensation
Total capacity
0 MW
Capacity effective from
31 October 2026
Connection site
Necton 400kV Substation
Transmission owner
National Grid (England & Wales)
Connection type
Direct connection to the transmission network
NESO project status
Consents Approved

Connection site

The marker shows the connection substation, not the project itself, with the transmission network around it.

Projects connecting near Necton · Grid map

Other projects at Necton 400kV Substation

Source: NESO Transmission Entry Capacity (TEC) register, downloaded 8 November 2026. Contains data from NESO, licensed under the NESO Open Data Licence. Report a problem