NESO TEC REGISTER · GREAT BRITAIN

Grid connection projects in the connection queue on the National Grid (England & Wales) network

Every generator, battery and interconnector with an agreement to connect to the GB transmission network, from early scoping to built. Filter by technology, stage or network, and open a project for its connection details.

Projects shown1,329586.0 GW in total
In planning968scoping or awaiting consent
Consented or building149closest to connecting
Built212connected and operating

Map

Loading projects…

Voltage400 kV275 kV132 kVHVDCNew HVAC

ProjectsPlanningConsentedConstructionBuiltMajor project with its own page

Projects

1,329 projects · page 1 of 27
ProjectCapacityStageConnection siteFrom
Bute Hydrogen Project 1
Gas · Haldane Energy Project 1 Limited
4.8 GWScoping Trent Valley South Connection Node D 400kV Substation
National Grid (England & Wales)
Oct 2035
Drax BECCS
Demand (data centres, industry) · Drax Power Limited
3.9 GWScoping Drax 400kV Substation
National Grid (England & Wales)
Oct 2035
Drax Power Station
Other · Drax Power Limited
3.9 GWBuilt Drax 400kV Substation
National Grid (England & Wales)
Bute Hydrogen Project 2
Gas · Haldane Energy Project 2 Limited
3.6 GWScoping Creyke Beck 400kV Substation
National Grid (England & Wales)
Oct 2035
Bute Hydrogen Project 3
Gas · Haldane Energy Project 3 Limited
3.6 GWScoping Grimsby West 400kV Substation
National Grid (England & Wales)
Oct 2035
Bute Hydrogen Project 5
Gas · Haldane Energy Project 5 Limited
3.6 GWScoping Teeside Connection Node B
National Grid (England & Wales)
Oct 2035
Bute Hydrogen Project 6
Gas · Haldane Energy Project 6 Limited
3.6 GWScoping Cheshire Connection Node A 400kV Substation
National Grid (England & Wales)
Oct 2037
Hinkley Point C
Nuclear · Nnb Generation Company (Hpc) Limited
3.3 GWScoping Shurton 400kV Substation
National Grid (England & Wales)
Jul 2030
Sizewell C
Nuclear · Sizewell C Limited
3.3 GWConsents Approved Sizewell 400kV Substation
National Grid (England & Wales)
Jul 2036
Hornsea Power Station 3
Offshore wind · Hornsea Project Three (UK) Limited
3.0 GWConsents Approved Norwich Main 400kV Substation
National Grid (England & Wales)
Dec 2028
Hornsea Power Station 4
Offshore wind · Orsted Hornsea Project Four Limited
2.6 GWScoping Creyke Beck 400kV Substation
National Grid (England & Wales)
Oct 2029
Portwind
Offshore wind · Se Portwind Ltd
2.5 GWScoping Chickerell 400kV Substation
National Grid (England & Wales)
Dec 2036
Eggborough CCGT - OCGT - BESS
Battery storage · Eggborough Power Limited
2.5 GWAwaiting Consents Eggborough 400kV Substation
National Grid (England & Wales)
Oct 2027
Bute Hydrogen Project 4
Gas · Haldane Energy Project 4 Limited
2.4 GWScoping Teeside Connection Node 2 C 132/400kV Substation
National Grid (England & Wales)
Oct 2035
Bute Hydrogen Project 7.1
Battery storage · Haldane Energy Project 7 Limited
2.4 GWScoping Solent Connection Node C 400kV
National Grid (England & Wales)
Oct 2038
Heysham Power Station
Nuclear · EDF Energy Nuclear Generation Limited
2.4 GWBuilt Heysham GSP
National Grid (England & Wales)
Hornsea Power Station 3
Offshore wind · Hornsea Project Three (UK) Limited
2.3 GWConsents Approved Norwich Main 400kV Substation
National Grid (England & Wales)
Oct 2026
Pembroke Power Station
Hydro and pumped storage · RWE Generation UK Plc
2.2 GWBuilt Pembroke 400kV Substation
National Grid (England & Wales)
Aquind Interconnector
Interconnector · Aquind Limited
2.1 GWAwaiting Consents Lovedean 400kV Substation
National Grid (England & Wales)
Jun 2030
Gallos
Offshore wind · Corio Generation Limited
2.0 GWScoping Alverdiscott 400kV Substation
National Grid (England & Wales)
Dec 2036
Walpole Flexible Generation
Battery storage · Flexible Generation 1 Ltd
2.0 GWScoping Walpole 400kV Substation
National Grid (England & Wales)
Jun 2033
Eggborough CCGT - OCGT - BESS
Battery storage · Eggborough Power Limited
2.0 GWAwaiting Consents Eggborough 400kV Substation
National Grid (England & Wales)
Oct 2026
IFA Interconnector
Interconnector · National Grid Interconnectors Limited
2.0 GWBuilt Sellindge 400kV Substation
National Grid (England & Wales)
West Burton B
Battery storage · West Burton B Limited
1.9 GWBuilt West Burton 400kV Substation
National Grid (England & Wales)
Oct 2034
West Burton B
Battery storage · West Burton B Limited
1.8 GWBuilt West Burton 400kV Substation
National Grid (England & Wales)
Oct 2027
Berwick Bank Offshore Wind Farm C
Offshore wind · Berwick Bank C Limited
1.8 GWScoping Blyth 400kV Substation
National Grid (England & Wales)
Nov 2029
Carrington Lane BESS
Battery storage · Apatura Battery Ltd
1.8 GWScoping Daines 400kV Substation
National Grid (England & Wales)
Oct 2037
Damhead Creek 2
Battery storage · VPI Power Limited
1.8 GWConsents Approved Kingsnorth 400kV Substation
National Grid (England & Wales)
Oct 2030
Alverdiscott
Interconnector · Xlinks 1 Ltd
1.8 GWScoping Alverdiscott 400kV Substation
National Grid (England & Wales)
Aug 2030
Alverdiscott 2
Interconnector · Xlinks 1 Ltd
1.8 GWScoping Alverdiscott 400kV Substation
National Grid (England & Wales)
Aug 2032
Continental Link
Interconnector · National Grid Interconnector Holdings Limited
1.8 GWScoping Birkhill Wood 400kV Substation
National Grid (England & Wales)
Oct 2035
Teeside MPI
Interconnector · National Grid Interconnector Holdings Limited
1.8 GWScoping Wearside Connection Node B 400kV Substation
National Grid (England & Wales)
Oct 2035
The Superconnection
Interconnector · Asc Energy plc
1.8 GWScoping Birkhill Wood 400kV Substation
National Grid (England & Wales)
Oct 2037
NatPower Enderby - Patford Bridge Green Energy Park
Battery storage · Enderby Energy Limited
1.8 GWScoping Derbyshire Connection Node G 400kV
National Grid (England & Wales)
Oct 2037
Staythorpe C
Gas · RWE Generation UK Plc
1.8 GWBuilt Staythorpe 400kV Substation
National Grid (England & Wales)
Didcot B
Battery storage · RWE Generation UK Plc
1.7 GWBuilt Didcot 400kV Substation
National Grid (England & Wales)
Oct 2037
Hinkley Point C
Nuclear · Nnb Generation Company (Hpc) Limited
1.7 GWScoping Shurton 400kV Substation
National Grid (England & Wales)
Mar 2029
Sizewell C
Nuclear · Sizewell C Limited
1.7 GWConsents Approved Sizewell 400kV Substation
National Grid (England & Wales)
Jul 2035
Dinorwig
Hydro and pumped storage · First Hydro Company
1.6 GWBuilt Dinorwig 400kV Substation
National Grid (England & Wales)
Springwell
Solar + storage · Springwell Energyfarm Limited
1.6 GWScoping Navenby 400kV Substation
National Grid (England & Wales)
Jun 2033
LionLink (EuroLink)
Interconnector · National Grid Interconnector Holdings Limited
1.6 GWScoping Friston 400kV Substation
National Grid (England & Wales)
Oct 2032
Grain
Gas · Uniper UK Limited
1.5 GWBuilt Grain 400kV Substation
National Grid (England & Wales)
GT R4 Offshore Wind Farm
Offshore wind · Gt R4 Limited
1.5 GWScoping Weston Marsh 400kV Substation
National Grid (England & Wales)
Nov 2030
Hornsea Power Station 4
Offshore wind · Orsted Hornsea Project Four Limited
1.5 GWScoping Creyke Beck 400kV Substation
National Grid (England & Wales)
Oct 2028
Mablethorpe Storage
Battery storage · Theddlethorpe Flexible Generation Limited
1.5 GWScoping Lincolnshire Coastal Node 400kV Substation
National Grid (England & Wales)
Nov 2031
Merlin 2 Offshore Windfarm
Offshore wind · Offshore Wind Limited
1.5 GWScoping Alverdiscott 400kV Substation
National Grid (England & Wales)
Oct 2031
Mona Offshore Wind Farm
Offshore wind · Mona Offshore Wind Limited
1.5 GWScoping Bodelwyddan 400kV Substation
National Grid (England & Wales)
Oct 2029
Morgan Offshore Wind Farm
Offshore wind · Morgan Offshore Wind Limited
1.5 GWScoping Penwortham 400kV Substation
National Grid (England & Wales)
Nov 2029
Morven A Offshore Wind Farm (Prev Phoenix 1A)
Offshore wind · Morven Offshore Wind Limited
1.5 GWScoping Hawthorn Pit 400kV Substation
National Grid (England & Wales)
Oct 2031
Nursling Flexible Generation
Gas · South Eng Flexible Generation Limited
1.5 GWScoping Nursling 400kV Substation
National Grid (England & Wales)
Oct 2038
Page 1 of 27

Sources: NESO Transmission Entry Capacity (TEC) register and interconnector register (downloaded 8 November 2026); NESO Clean Power 2030 network map (existing and planned circuits, substations and network projects); National Grid Electricity Transmission overhead line routes. Contains data from NESO, licensed under the NESO Open Data Licence, and National Grid open data. Projects are placed at their connection substation, not the generating site; projects at new, unnamed “connection nodes” are listed but not mapped.