Grid infrastructure › Connection queue › Offshore wind

OFFSHORE WIND · NGET

Hornsea Power Station 4

Hornsea Power Station 4 is a 2.6 GW offshore wind project in planning, connecting to the National Grid (England & Wales) network at Creyke Beck 400kV Substation, with capacity due from October 2029. The connection agreement is held by Orsted Hornsea Project Four Limited.

Project stageIn planning
  1. Planning (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingFrom Oct 2029 (not yet reached)
  5. Closed (not yet reached)

Scoping and awaiting consents are both shown as planning. A connection agreement does not mean the project will be built: many queue projects never reach construction.

Connection details

NESO project number
PRO-000435-2
Customer
Orsted Hornsea Project Four Limited
Technology
Wind Offshore
Total capacity
2.6 GW
Change in this agreement
+1.1 GW
Capacity effective from
31 October 2029
Connection site
Creyke Beck 400kV Substation
Transmission owner
National Grid (England & Wales)
Connection type
Direct connection to the transmission network
NESO project status
Scoping

Connection site

The marker shows the connection substation, not the project itself, with the transmission network around it.

Projects connecting near Creyke Beck · Grid map

Other projects at Creyke Beck 400kV Substation

Source: NESO Transmission Entry Capacity (TEC) register, downloaded 8 November 2026. Contains data from NESO, licensed under the NESO Open Data Licence. Report a problem