Grid infrastructure › Connection queue › Battery storage
BATTERY STORAGE · NGETWalpole Flexible Generation
Walpole Flexible Generation is a 2.0 GW battery storage project in planning, connecting to the National Grid (England & Wales) network at Walpole 400kV Substation, with capacity due from June 2033. The connection agreement is held by Flexible Generation 1 Ltd.
- Planning (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingFrom Jun 2033 (not yet reached)
- Closed (not yet reached)
Scoping and awaiting consents are both shown as planning. A connection agreement does not mean the project will be built: many queue projects never reach construction.
Connection details
- NESO project number
- PRO-002440
- Customer
- Flexible Generation 1 Ltd
- Technology
- CCGT (Combined Cycle Gas Turbine), Energy Storage System
- Total capacity
- 2.0 GW
- Change in this agreement
- +2.0 GW
- Capacity effective from
- 30 June 2033
- Connection site
- Walpole 400kV Substation
- Transmission owner
- National Grid (England & Wales)
- Connection type
- Direct connection to the transmission network
- NESO project status
- Scoping
Connection site
The marker shows the connection substation, not the project itself, with the transmission network around it.
Other projects at Walpole 400kV Substation
Source: NESO Transmission Entry Capacity (TEC) register, downloaded 8 November 2026. Contains data from NESO, licensed under the NESO Open Data Licence. Report a problem