Walpole Grid Services Facility

Walpole Grid Services Facility is a 0 MW other project consented, connecting to the National Grid (England & Wales) network at Walpole 400kV Substation, with capacity due from July 2026. The connection agreement is held by Conrad (Walpole) Limited.

Project stageConsented
  1. Planning (completed)
  2. Consented (current stage)
  3. Construction (not yet reached)
  4. OperatingFrom Jul 2026 (not yet reached)
  5. Closed (not yet reached)

Connection details

NESO project number
PRO-003728
Customer
Conrad (Walpole) Limited
Technology
Reactive Compensation
Total capacity
0 MW
Capacity effective from
13 July 2026
Connection site
Walpole 400kV Substation
Transmission owner
National Grid (England & Wales)
Connection type
Direct connection to the transmission network
NESO project status
Consents Approved

Connection site

The marker shows the connection substation, not the project itself, with the transmission network around it.

Projects connecting near Walpole Β· Grid map