Grid infrastructure › Connection queue › Battery storage

BATTERY STORAGE · NGET

Eggborough CCGT - OCGT - BESS

Eggborough CCGT - OCGT - BESS is a 2.5 GW battery storage project in planning, connecting to the National Grid (England & Wales) network at Eggborough 400kV Substation, with capacity due from October 2027. The connection agreement is held by Eggborough Power Limited.

Project stageIn planning
  1. Planning (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingFrom Oct 2027 (not yet reached)
  5. Closed (not yet reached)

Scoping and awaiting consents are both shown as planning. A connection agreement does not mean the project will be built: many queue projects never reach construction.

Connection details

NESO project number
PRO-000136-2
Customer
Eggborough Power Limited
Technology
CCGT (Combined Cycle Gas Turbine), Energy Storage System, OCGT (Open Cycle Gas Turbine)
Total capacity
2.5 GW
Change in this agreement
+451 MW
Capacity effective from
1 October 2027
Connection site
Eggborough 400kV Substation
Transmission owner
National Grid (England & Wales)
Connection type
Direct connection to the transmission network
NESO project status
Awaiting Consents

Connection site

The marker shows the connection substation, not the project itself, with the transmission network around it.

Projects connecting near Eggborough · Grid map

Other projects at Eggborough 400kV Substation

Source: NESO Transmission Entry Capacity (TEC) register, downloaded 8 November 2026. Contains data from NESO, licensed under the NESO Open Data Licence. Report a problem