Coryton is a 850 MW gas project built and connected, connecting to the National Grid (England & Wales) network at Coryton South 400kV Substation. The connection agreement is held by Coryton Energy Company, Ltd..
Connection details
- NESO project number
- PRO-000103
- Customer
- Coryton Energy Company, Ltd.
- Technology
- CCGT (Combined Cycle Gas Turbine)
- Total capacity
- 850 MW
- Already connected
- 800 MW
- Change in this agreement
- +50 MW
- Capacity effective from
- 30 October 2029
- Connection site
- Coryton South 400kV Substation
- Transmission owner
- National Grid (England & Wales)
- Connection type
- Direct connection to the transmission network
- NESO project status
- Built
Connection site
The marker shows the connection substation, not the project itself, with the transmission network around it.
Other projects at Coryton South 400kV Substation
Source: NESO Transmission Entry Capacity (TEC) register, downloaded 8 November 2026. Contains data from NESO, licensed under the NESO Open Data Licence. Report a problem