Grid infrastructure › Connection queue › Offshore wind

OFFSHORE WIND · NGET

East Anglia One North

East Anglia One North is a 860 MW offshore wind project in planning, connecting to the National Grid (England & Wales) network at Friston 400kV Substation, with capacity due from October 2029. The connection agreement is held by East Anglia One North Limited.

Project stageIn planning
  1. Planning (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingFrom Oct 2029 (not yet reached)
  5. Closed (not yet reached)

Scoping and awaiting consents are both shown as planning. A connection agreement does not mean the project will be built: many queue projects never reach construction.

Connection details

NESO project number
PRO-000269-1
Customer
East Anglia One North Limited
Technology
Wind Offshore
Total capacity
860 MW
Change in this agreement
+860 MW
Capacity effective from
30 October 2029
Connection site
Friston 400kV Substation
Transmission owner
National Grid (England & Wales)
Connection type
Direct connection to the transmission network
NESO project status
Awaiting Consents

Connection site

The connection site could not be placed on the map.

Projects connecting near Friston · Grid map

Other projects at Friston 400kV Substation

Source: NESO Transmission Entry Capacity (TEC) register, downloaded 8 November 2026. Contains data from NESO, licensed under the NESO Open Data Licence. Report a problem