Grid infrastructure β€Ί Connection queue β€Ί Gas

GAS Β· NGET

Keadby II

Keadby II is a 893 MW gas project built and connected, connecting to the National Grid (England & Wales) network at Keadby 400kV Substation. The connection agreement is held by Keadby Generation Limited.

Project stageOperating
  1. Planning (completed)
  2. Consented (completed)
  3. Construction (completed)
  4. Operating (current stage)
  5. Closed (not yet reached)

Connection details

NESO project number
PRO-000310
Customer
Keadby Generation Limited
Technology
CCGT (Combined Cycle Gas Turbine)
Total capacity
893 MW
Already connected
893 MW
Connection site
Keadby 400kV Substation
Transmission owner
National Grid (England & Wales)
Connection type
Direct connection to the transmission network
NESO project status
Built

Connection site

The marker shows the connection substation, not the project itself, with the transmission network around it.

Projects connecting near Keadby Β· Grid map

Other projects at Keadby 400kV Substation

Source: NESO Transmission Entry Capacity (TEC) register, downloaded 8 November 2026. Contains data from NESO, licensed under the NESO Open Data Licence. Report a problem