Thornton Facility

Thornton Facility is a 930 MW solar + storage project consented, connecting to the National Grid (England & Wales) network at Thornton 400kV Substation, with capacity due from October 2032. The connection agreement is held by Balwen Limited.

Project stageConsented
  1. Planning (completed)
  2. Consented (current stage)
  3. Construction (not yet reached)
  4. OperatingFrom Oct 2032 (not yet reached)
  5. Closed (not yet reached)

Connection details

NESO project number
PRO-001484-4
Customer
Balwen Limited
Technology
Energy Storage System, PV Array (Photo Voltaic/solar)
Total capacity
930 MW
Change in this agreement
+530 MW
Capacity effective from
29 October 2032
Connection site
Thornton 400kV Substation
Transmission owner
National Grid (England & Wales)
Connection type
Direct connection to the transmission network
NESO project status
Consents Approved

Connection site

The marker shows the connection substation, not the project itself, with the transmission network around it.

Projects connecting near Thornton Β· Grid map

Other projects at Thornton 400kV Substation

Source: NESO Transmission Entry Capacity (TEC) register, downloaded 8 November 2026. Contains data from NESO, licensed under the NESO Open Data Licence. Report a problem