Medway Power Station

Medway Power Station is a 910 MW gas project built and connected, connecting to the National Grid (England & Wales) network at Grain 400kV Substation. The connection agreement is held by Medway Power Limited.

Project stageOperating
  1. Planning (completed)
  2. Consented (completed)
  3. Construction (completed)
  4. OperatingOct 2028 (current stage)
  5. Closed (not yet reached)

Connection details

NESO project number
PRO-000203
Customer
Medway Power Limited
Technology
CCGT (Combined Cycle Gas Turbine)
Total capacity
910 MW
Already connected
735 MW
Change in this agreement
+175 MW
Capacity effective from
30 October 2028
Connection site
Grain 400kV Substation
Transmission owner
National Grid (England & Wales)
Connection type
Direct connection to the transmission network
NESO project status
Built

Connection site

The marker shows the connection substation, not the project itself, with the transmission network around it.

Projects connecting near Grain Β· Grid map

Other projects at Grain 400kV Substation

Source: NESO Transmission Entry Capacity (TEC) register, downloaded 8 November 2026. Contains data from NESO, licensed under the NESO Open Data Licence. Report a problem