Grid infrastructure › Connection queue › Battery storage

BATTERY STORAGE · NGET

Fiddlers Ferry BESS

Fiddlers Ferry BESS is a 900 MW battery storage project consented, connecting to the National Grid (England & Wales) network at Fiddlers Ferry 275kV Substation, with capacity due from October 2029. The connection agreement is held by Fiddlers Ferry Ltd.

Project stageConsented
  1. Planning (completed)
  2. Consented (current stage)
  3. Construction (not yet reached)
  4. OperatingFrom Oct 2029 (not yet reached)
  5. Closed (not yet reached)

Connection details

NESO project number
PRO-003897-3
Customer
Fiddlers Ferry Ltd
Technology
Demand, Energy Storage System
Total capacity
900 MW
Change in this agreement
+300 MW
Capacity effective from
31 October 2029
Connection site
Fiddlers Ferry 275kV Substation
Transmission owner
National Grid (England & Wales)
Connection type
Direct connection to the transmission network
NESO project status
Consents Approved
Connections reform gate
Gate 2

Connection site

The marker shows the connection substation, not the project itself, with the transmission network around it.

Projects connecting near Fiddlers Ferry · Grid map

Other projects at Fiddlers Ferry 275kV Substation

Source: NESO Transmission Entry Capacity (TEC) register, downloaded 8 November 2026. Contains data from NESO, licensed under the NESO Open Data Licence. Report a problem