🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

Home › Grid infrastructure › Connection queue

NESO TEC REGISTER · GREAT BRITAIN

Grid connection projects in the connection queue on the SSEN Transmission (north Scotland) network

Every generator, battery and interconnector with an agreement to connect to the GB transmission network, from early scoping to built. Filter by technology, stage or network, and open a project for its connection details.

Projects shown30385.5 GW in total
In planning303scoping or awaiting consent
Consented or building52closest to connecting
Built89connected and operating

Map

Loading projects…

Voltage400 kV275 kV132 kVHVDCNew HVAC

ProjectsPlanningConsentedConstructionBuiltMajor project with its own page

Projects

303 projects · page 4 of 7
ProjectCapacityStageConnection siteFrom
Aultmore Wind Farm (2023)
Wind + storage · Vattenfall Wind Power Ltd
105 MWScoping Aultmore Wind Farm 132/33kV Substation
SSEN Transmission (north Scotland)
Sep 2030
Creag Riabhach Wind Farm
Onshore wind · Creag Riabhach Wind Farm Ltd
105 MWScoping Creag Riabhach 132/33kV Substation
SSEN Transmission (north Scotland)
Jul 2027
Earraghail Renewable Energy Development (formerly Skipness & Corranbuie)
Solar + storage · Scottish Power Renewables (UK) Limited
105 MWScoping Earraghail 275/33KV Substation
SSEN Transmission (north Scotland)
Apr 2031
Eredine Wind Farm
Wind + storage · RWE Renewables UK Onshore Wind Limited
105 MWScoping An Suidhe 275/33kV
SSEN Transmission (north Scotland)
Nov 2029
Fasque Windfarm
Solar · Scottish Power Renewables (UK) Limited
105 MWScoping Fetteresso 132kV substation
SSEN Transmission (north Scotland)
Oct 2031
Kinmuck PV and BESS Station
Solar + storage · Kinmuck Energy Storage Limited
105 MWAwaiting Consents Kinmuck BESS 132kV Substation
SSEN Transmission (north Scotland)
May 2027
Ourack Wind Farm
Wind + storage · Ourack Wind Farm LLP
105 MWScoping Ourack Wind Farm 132/33 kV Substation
SSEN Transmission (north Scotland)
Oct 2030
Glentarken Wind Farm
Onshore wind · SSE Renewables Services (UK) Limited
104 MWScoping Glentarken Wind Farm 132/33Kv Substation
SSEN Transmission (north Scotland)
Nov 2031
Bhlaraidh Extension Wind Farm
Onshore wind · Sse Generation Limited
101 MWScoping Bhlaraidh 132/33kV Substation
SSEN Transmission (north Scotland)
Aug 2029
Cruach Bhreac Wind Farm
Onshore wind · Statkraft UK Ltd
101 MWScoping Craig Murrail 275kV Substation
SSEN Transmission (north Scotland)
Oct 2034
Dunach Wind Farm
Onshore wind · Galileo 04 Limited
101 MWScoping Dunach Wind 132Kv Substation
SSEN Transmission (north Scotland)
Oct 2034
Statkraft SEWF
Onshore wind · Statkraft UK Ltd
101 MWScoping Orrin GSP
SSEN Transmission (north Scotland)
Oct 2033
Beauly 02 BESS
Battery storage · Field Beauly Ltd
100 MWScoping BEAULY 02 BESS 132kV SUBSTATION
SSEN Transmission (north Scotland)
Dec 2028
Cott's Farm
Solar + storage · Boralex Limited
100 MWScoping Cott's Farm 132kV Substation
SSEN Transmission (north Scotland)
Oct 2034
Farm 100MW BESS
Battery storage · Apatura Battery Ltd
100 MWScoping Thurso South 275kV Substation
SSEN Transmission (north Scotland)
Oct 2033
Scaraben Offshore Wind Farm
Offshore wind · Scaraben Offshore Wind Farm Limited
100 MWScoping Longside 132kV Substation
SSEN Transmission (north Scotland)
Oct 2033
Sheilhill Battery Storage
Battery storage · Sheilhill Battery Storage Limited
100 MWAwaiting Consents St Fergus 132Kv Switching Station
SSEN Transmission (north Scotland)
Oct 2033
Sinclair Offshore Wind Farm
Offshore wind · Sinclair Offshore Wind Farm Limited
100 MWScoping Longside 132kV Substation
SSEN Transmission (north Scotland)
Oct 2033
Sleat Hybrid
Wind + storage · Galileo 13 Limited
100 MWScoping Broadford GSP
SSEN Transmission (north Scotland)
Oct 2034
St Fergus
Solar + storage · Ib Vogt UK Ltd
100 MWScoping St Fergus
SSEN Transmission (north Scotland)
Oct 2033
Thurso South BESS
Battery storage · WP Grid Storage 3 Limited
100 MWScoping Thurso South 275kV Substation
SSEN Transmission (north Scotland)
Oct 2030
Breakish Windfarm
Onshore wind · Asuk Holdco 2 Limited
100 MWScoping Breakish 132kV Substation
SSEN Transmission (north Scotland)
Apr 2034
Brunt Hill Wind Farm
Wind + storage · Brunt Hill Limited
99 MWAwaiting Consents Westfield 132/33kV
SSEN Transmission (north Scotland)
Oct 2031
Car Duibh Wind Farm
Onshore wind · Car Duibh Wind Farm Limited
99 MWAwaiting Consents Car Duibh 275kV Substation
SSEN Transmission (north Scotland)
Oct 2034
Elchies Wind Farm
Onshore wind · Elchies Wind Limited
99 MWScoping Elchies 132/33kV Substation
SSEN Transmission (north Scotland)
Nov 2028
Forsinain Wind Farm
Onshore wind · Forsinain Forest Wind Farm Limited
99 MWScoping Connagill 132kV Substation
SSEN Transmission (north Scotland)
Oct 2037
Loch Liath Wind Farm
Onshore wind · Loch Liath Wind Farm Limited
99 MWAwaiting Consents Loch Liath 132/33kV Substation
SSEN Transmission (north Scotland)
Oct 2035
Quintfall Forest Hybrid Wind and BESS 1
Wind + storage · Voltalia UK Ltd
99 MWScoping Gills Bay 132kV
SSEN Transmission (north Scotland)
Oct 2037
Ballygroggan Wind Farm
Onshore wind · Dalriada Renewables Limited
96 MWScoping Ballygroggan 132/33Kv Substation
SSEN Transmission (north Scotland)
Oct 2034
Tangy IV WF
Onshore wind · SSE Renewables Services (UK) Limited
96 MWScoping Tangy IV 132KV Substation
SSEN Transmission (north Scotland)
Apr 2029
17 Acres and BESS
Battery storage · Aeuk Battery Project II Ltd
96 MWScoping 17 Acres BESS 275Kv Substation
SSEN Transmission (north Scotland)
Jun 2032
Beinn an Tuirc 1
Onshore wind · Scottish Power Renewables (UK) Limited
95 MWScoping Beinn an Tuirc Substation
SSEN Transmission (north Scotland)
Oct 2034
Braegrundie Farm
Battery storage · Aeuk Battery Project III Ltd
95 MWAwaiting Consents Braegrundie Farm 132kV Substation
SSEN Transmission (north Scotland)
Jun 2030
Pollie Hill Wind Farm
Onshore wind · Pollie Hill Wind Farm Limited
92 MWScoping Pollie Hill Wind Farm 132Kv Substation
SSEN Transmission (north Scotland)
Oct 2031
Kyllachy Wind Farm
Wind + storage · Wind Estate (UK) Limited
91 MWScoping Tomatin 132kV Substation Extension
SSEN Transmission (north Scotland)
Oct 2037
Breackerie wind farm
Wind + storage · Energyfarm UK Breackerie Ltd
91 MWScoping Breackerie 132kV Substation
SSEN Transmission (north Scotland)
Oct 2037
Rowan Wind Energyfarm
Wind + storage · Energyfarm Rowan LLP
91 MWScoping Rowan 275/33kV Substation
SSEN Transmission (north Scotland)
Oct 2034
Edinbane Windfarm
Wind + storage · Vattenfall Wind Power Ltd
90 MWScoping Edinbane 132/33kV Substation
SSEN Transmission (north Scotland)
Apr 2033
Fairburn Extension Wind Farm
Onshore wind · SSE Renewables Services (UK) Limited
90 MWScoping Fairburn Extension 132/33kV Substation
SSEN Transmission (north Scotland)
Oct 2031
Kellas Wind Farm
Onshore wind · E Power Limited
90 MWScoping Kellas Wind Farm 132kV Substation
SSEN Transmission (north Scotland)
Oct 2030
Woodcock Hill Wind Farm
Wind + storage · Perigus Energy UK Limited
90 MWScoping Woodcock Hill WF Substation
SSEN Transmission (north Scotland)
Oct 2032
Ceislein Wind Farm
Onshore wind · RWE Renewables UK Onshore Wind Limited
86 MWScoping Ceislien Wind Farm
SSEN Transmission (north Scotland)
Oct 2030
Carn Fearna Wind Farm
Onshore wind · Carn Fearna Wind Farm Limited
85 MWScoping Carn Fearna Wind Farm 132/33kV Substation
SSEN Transmission (north Scotland)
Jun 2030
Acheilidh Wind Farm
Wind + storage · Energyfarm UK Acheilidh Ltd
84 MWScoping Acheilidh Wind farm 132kV Substation
SSEN Transmission (north Scotland)
Oct 2033
Beinn Tharsuinn Repower
Onshore wind · Scottish Power Renewables (UK) Limited
84 MWScoping Beinn Thursunn Repower 275/33Kv
SSEN Transmission (north Scotland)
Oct 2029
Lynemore Wind Farm
Onshore wind · Galileo Empower UK Limited
84 MWScoping Lynemore Windfarm 132kV Substation
SSEN Transmission (north Scotland)
Oct 2031
Sheirdrim Wind Farm
Onshore wind · Scottish Power Renewables (UK) Limited
84 MWScoping Sheirdrim 132kV Substation
SSEN Transmission (north Scotland)
Apr 2032
Kirkan Wind Farm
Wind + storage · Kirkan Wind Farm Limited
82 MWScoping Corriemoillie 2 400/132kV Substation
SSEN Transmission (north Scotland)
Oct 2033
Caorach
Wind + storage · Invenergy Development UK Ltd
81 MWScoping Caorach 132 KV Substation
SSEN Transmission (north Scotland)
Oct 2033
Tealing Solar & Storage
Solar + storage · Sirius Ecodev (Tealing) Ltd
80 MWAwaiting Consents Tealing IDNO 132/33kV GSP
SSEN Transmission (north Scotland)
Oct 2028

Sources: NESO Transmission Entry Capacity (TEC) register and interconnector register (downloaded 8 November 2026); NESO Clean Power 2030 network map (existing and planned circuits, substations and network projects); National Grid Electricity Transmission overhead line routes. Contains data from NESO, licensed under the NESO Open Data Licence, and National Grid open data. Projects are placed at their connection substation, not the generating site; projects at new, unnamed “connection nodes” are listed but not mapped.