Home › Grid infrastructure › Connection queue
NESO TEC REGISTER · GREAT BRITAINGrid connection projects in the connection queue on the SSEN Transmission (north Scotland) network
Every generator, battery and interconnector with an agreement to connect to the GB transmission network, from early scoping to built. Filter by technology, stage or network, and open a project for its connection details.
Map
Voltage400 kV275 kV132 kVHVDCNew HVAC
ProjectsPlanningConsentedConstructionBuiltMajor project with its own page
Projects
| Project | Capacity | Stage |
|---|---|---|
| Aultmore Wind Farm (2023) Wind + storage · Vattenfall Wind Power Ltd |
105 MW | Scoping |
| Creag Riabhach Wind Farm Onshore wind · Creag Riabhach Wind Farm Ltd |
105 MW | Scoping |
| Earraghail Renewable Energy Development (formerly Skipness & Corranbuie) Solar + storage · Scottish Power Renewables (UK) Limited |
105 MW | Scoping |
| Eredine Wind Farm Wind + storage · RWE Renewables UK Onshore Wind Limited |
105 MW | Scoping |
| Fasque Windfarm Solar · Scottish Power Renewables (UK) Limited |
105 MW | Scoping |
| Kinmuck PV and BESS Station Solar + storage · Kinmuck Energy Storage Limited |
105 MW | Awaiting Consents |
| Ourack Wind Farm Wind + storage · Ourack Wind Farm LLP |
105 MW | Scoping |
| Glentarken Wind Farm Onshore wind · SSE Renewables Services (UK) Limited |
104 MW | Scoping |
| Bhlaraidh Extension Wind Farm Onshore wind · Sse Generation Limited |
101 MW | Scoping |
| Cruach Bhreac Wind Farm Onshore wind · Statkraft UK Ltd |
101 MW | Scoping |
| Dunach Wind Farm Onshore wind · Galileo 04 Limited |
101 MW | Scoping |
| Statkraft SEWF Onshore wind · Statkraft UK Ltd |
101 MW | Scoping |
| Beauly 02 BESS Battery storage · Field Beauly Ltd |
100 MW | Scoping |
| Cott's Farm Solar + storage · Boralex Limited |
100 MW | Scoping |
| Farm 100MW BESS Battery storage · Apatura Battery Ltd |
100 MW | Scoping |
| Scaraben Offshore Wind Farm Offshore wind · Scaraben Offshore Wind Farm Limited |
100 MW | Scoping |
| Sheilhill Battery Storage Battery storage · Sheilhill Battery Storage Limited |
100 MW | Awaiting Consents |
| Sinclair Offshore Wind Farm Offshore wind · Sinclair Offshore Wind Farm Limited |
100 MW | Scoping |
| Sleat Hybrid Wind + storage · Galileo 13 Limited |
100 MW | Scoping |
| St Fergus Solar + storage · Ib Vogt UK Ltd |
100 MW | Scoping |
| Thurso South BESS Battery storage · WP Grid Storage 3 Limited |
100 MW | Scoping |
| Breakish Windfarm Onshore wind · Asuk Holdco 2 Limited |
100 MW | Scoping |
| Brunt Hill Wind Farm Wind + storage · Brunt Hill Limited |
99 MW | Awaiting Consents |
| Car Duibh Wind Farm Onshore wind · Car Duibh Wind Farm Limited |
99 MW | Awaiting Consents |
| Elchies Wind Farm Onshore wind · Elchies Wind Limited |
99 MW | Scoping |
| Forsinain Wind Farm Onshore wind · Forsinain Forest Wind Farm Limited |
99 MW | Scoping |
| Loch Liath Wind Farm Onshore wind · Loch Liath Wind Farm Limited |
99 MW | Awaiting Consents |
| Quintfall Forest Hybrid Wind and BESS 1 Wind + storage · Voltalia UK Ltd |
99 MW | Scoping |
| Ballygroggan Wind Farm Onshore wind · Dalriada Renewables Limited |
96 MW | Scoping |
| Tangy IV WF Onshore wind · SSE Renewables Services (UK) Limited |
96 MW | Scoping |
| 17 Acres and BESS Battery storage · Aeuk Battery Project II Ltd |
96 MW | Scoping |
| Beinn an Tuirc 1 Onshore wind · Scottish Power Renewables (UK) Limited |
95 MW | Scoping |
| Braegrundie Farm Battery storage · Aeuk Battery Project III Ltd |
95 MW | Awaiting Consents |
| Pollie Hill Wind Farm Onshore wind · Pollie Hill Wind Farm Limited |
92 MW | Scoping |
| Kyllachy Wind Farm Wind + storage · Wind Estate (UK) Limited |
91 MW | Scoping |
| Breackerie wind farm Wind + storage · Energyfarm UK Breackerie Ltd |
91 MW | Scoping |
| Rowan Wind Energyfarm Wind + storage · Energyfarm Rowan LLP |
91 MW | Scoping |
| Edinbane Windfarm Wind + storage · Vattenfall Wind Power Ltd |
90 MW | Scoping |
| Fairburn Extension Wind Farm Onshore wind · SSE Renewables Services (UK) Limited |
90 MW | Scoping |
| Kellas Wind Farm Onshore wind · E Power Limited |
90 MW | Scoping |
| Woodcock Hill Wind Farm Wind + storage · Perigus Energy UK Limited |
90 MW | Scoping |
| Ceislein Wind Farm Onshore wind · RWE Renewables UK Onshore Wind Limited |
86 MW | Scoping |
| Carn Fearna Wind Farm Onshore wind · Carn Fearna Wind Farm Limited |
85 MW | Scoping |
| Acheilidh Wind Farm Wind + storage · Energyfarm UK Acheilidh Ltd |
84 MW | Scoping |
| Beinn Tharsuinn Repower Onshore wind · Scottish Power Renewables (UK) Limited |
84 MW | Scoping |
| Lynemore Wind Farm Onshore wind · Galileo Empower UK Limited |
84 MW | Scoping |
| Sheirdrim Wind Farm Onshore wind · Scottish Power Renewables (UK) Limited |
84 MW | Scoping |
| Kirkan Wind Farm Wind + storage · Kirkan Wind Farm Limited |
82 MW | Scoping |
| Caorach Wind + storage · Invenergy Development UK Ltd |
81 MW | Scoping |
| Tealing Solar & Storage Solar + storage · Sirius Ecodev (Tealing) Ltd |
80 MW | Awaiting Consents |
Sources: NESO Transmission Entry Capacity (TEC) register and interconnector register (downloaded 8 November 2026); NESO Clean Power 2030 network map (existing and planned circuits, substations and network projects); National Grid Electricity Transmission overhead line routes. Contains data from NESO, licensed under the NESO Open Data Licence, and National Grid open data. Projects are placed at their connection substation, not the generating site; projects at new, unnamed “connection nodes” are listed but not mapped.