Grid infrastructure βΊ Connection queue βΊ Onshore wind
ONSHORE WIND Β· SHETTangy IV WF
Tangy IV WF is a 96 MW onshore wind project in planning, connecting to the SSEN Transmission (north Scotland) network at Tangy IV 132KV Substation, with capacity due from April 2029. The connection agreement is held by SSE Renewables Services (UK) Limited.
- Planning (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingFrom Apr 2029 (not yet reached)
- Closed (not yet reached)
Scoping and awaiting consents are both shown as planning. A connection agreement does not mean the project will be built: many queue projects never reach construction.
Connection details
- NESO project number
- PRO-001408
- Customer
- SSE Renewables Services (UK) Limited
- Technology
- Substation, Wind Onshore
- Total capacity
- 96 MW
- Change in this agreement
- +96 MW
- Capacity effective from
- 30 April 2029
- Connection site
- Tangy IV 132KV Substation
- Transmission owner
- SSEN Transmission (north Scotland)
- Connection type
- Direct connection to the transmission network
- NESO project status
- Scoping
Connection site
The connection site could not be placed on the map.
Source: NESO Transmission Entry Capacity (TEC) register, downloaded 8 November 2026. Contains data from NESO, licensed under the NESO Open Data Licence. Report a problem