BATTERY STORAGE · SHETBraegrundie Farm
Braegrundie Farm is a 95 MW battery storage project in planning, connecting to the SSEN Transmission (north Scotland) network at Braegrundie Farm 132kV Substation, with capacity due from June 2030. The connection agreement is held by Aeuk Battery Project III Ltd.
- Planning (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingFrom Jun 2030 (not yet reached)
- Closed (not yet reached)
Scoping and awaiting consents are both shown as planning. A connection agreement does not mean the project will be built: many queue projects never reach construction.
Connection details
- NESO project number
- PRO-004674
- Customer
- Aeuk Battery Project III Ltd
- Technology
- Energy Storage System
- Total capacity
- 95 MW
- Change in this agreement
- +95 MW
- Capacity effective from
- 30 June 2030
- Connection site
- Braegrundie Farm 132kV Substation
- Transmission owner
- SSEN Transmission (north Scotland)
- Connection type
- Direct connection to the transmission network
- NESO project status
- Awaiting Consents
- Connections reform gate
- Gate 1
Connection site
The connection site could not be placed on the map.
Source: NESO Transmission Entry Capacity (TEC) register, downloaded 8 November 2026. Contains data from NESO, licensed under the NESO Open Data Licence. Report a problem