BATTERY STORAGE · SHET

Braegrundie Farm

Braegrundie Farm is a 95 MW battery storage project in planning, connecting to the SSEN Transmission (north Scotland) network at Braegrundie Farm 132kV Substation, with capacity due from June 2030. The connection agreement is held by Aeuk Battery Project III Ltd.

Project stageIn planning
  1. Planning (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingFrom Jun 2030 (not yet reached)
  5. Closed (not yet reached)

Scoping and awaiting consents are both shown as planning. A connection agreement does not mean the project will be built: many queue projects never reach construction.

Connection details

NESO project number
PRO-004674
Customer
Aeuk Battery Project III Ltd
Technology
Energy Storage System
Total capacity
95 MW
Change in this agreement
+95 MW
Capacity effective from
30 June 2030
Connection site
Braegrundie Farm 132kV Substation
Transmission owner
SSEN Transmission (north Scotland)
Connection type
Direct connection to the transmission network
NESO project status
Awaiting Consents
Connections reform gate
Gate 1

Connection site

The connection site could not be placed on the map.

Projects connecting near Braegrundie Farm · Grid map