Grid infrastructure › Connection queue › Wind + storage

WIND + STORAGE · SHET

Quintfall Forest Hybrid Wind and BESS 1

Quintfall Forest Hybrid Wind and BESS 1 is a 99 MW wind + storage project in planning, connecting to the SSEN Transmission (north Scotland) network at Gills Bay 132kV, with capacity due from October 2037. The connection agreement is held by Voltalia UK Ltd.

Project stageIn planning
  1. Planning (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingFrom Oct 2037 (not yet reached)
  5. Closed (not yet reached)

Scoping and awaiting consents are both shown as planning. A connection agreement does not mean the project will be built: many queue projects never reach construction.

Connection details

NESO project number
PRO-006032
Customer
Voltalia UK Ltd
Technology
Energy Storage System, Wind Onshore
Total capacity
99 MW
Change in this agreement
+99 MW
Capacity effective from
31 October 2037
Connection site
Gills Bay 132kV
Transmission owner
SSEN Transmission (north Scotland)
Connection type
Direct connection to the transmission network
NESO project status
Scoping
Connections reform gate
Gate 1

Connection site

The connection site could not be placed on the map.

Projects connecting near Gills Bay · Grid map

Other projects at Gills Bay 132kV

Source: NESO Transmission Entry Capacity (TEC) register, downloaded 8 November 2026. Contains data from NESO, licensed under the NESO Open Data Licence. Report a problem