Grid infrastructure › Connection queue › Solar + storage
SOLAR + STORAGE · SHETEarraghail Renewable Energy Development (formerly Skipness & Corranbuie)
Earraghail Renewable Energy Development (formerly Skipness & Corranbuie) is a 105 MW solar + storage project in planning, connecting to the SSEN Transmission (north Scotland) network at Earraghail 275/33KV Substation, with capacity due from April 2031. The connection agreement is held by Scottish Power Renewables (UK) Limited.
- Planning (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingFrom Apr 2031 (not yet reached)
- Closed (not yet reached)
Scoping and awaiting consents are both shown as planning. A connection agreement does not mean the project will be built: many queue projects never reach construction.
Connection details
- NESO project number
- PRO-001139
- Customer
- Scottish Power Renewables (UK) Limited
- Technology
- Energy Storage System, PV Array (Photo Voltaic/solar), Wind Onshore
- Total capacity
- 105 MW
- Change in this agreement
- +105 MW
- Capacity effective from
- 1 April 2031
- Connection site
- Earraghail 275/33KV Substation
- Transmission owner
- SSEN Transmission (north Scotland)
- Connection type
- Direct connection to the transmission network
- NESO project status
- Scoping
Connection site
The connection site could not be placed on the map.
Source: NESO Transmission Entry Capacity (TEC) register, downloaded 8 November 2026. Contains data from NESO, licensed under the NESO Open Data Licence. Report a problem