Grid infrastructure › Connection queue › Wind + storage
WIND + STORAGE · SHETRowan Wind Energyfarm
Rowan Wind Energyfarm is a 91 MW wind + storage project in planning, connecting to the SSEN Transmission (north Scotland) network at Rowan 275/33kV Substation, with capacity due from October 2034. The connection agreement is held by Energyfarm Rowan LLP.
- Planning (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingFrom Oct 2034 (not yet reached)
- Closed (not yet reached)
Scoping and awaiting consents are both shown as planning. A connection agreement does not mean the project will be built: many queue projects never reach construction.
Connection details
- NESO project number
- PRO-003823
- Customer
- Energyfarm Rowan LLP
- Technology
- Energy Storage System, Wind Onshore
- Total capacity
- 91 MW
- Change in this agreement
- +91 MW
- Capacity effective from
- 31 October 2034
- Connection site
- Rowan 275/33kV Substation
- Transmission owner
- SSEN Transmission (north Scotland)
- Connection type
- Direct connection to the transmission network
- NESO project status
- Scoping
Connection site
The connection site could not be placed on the map.
Source: NESO Transmission Entry Capacity (TEC) register, downloaded 8 November 2026. Contains data from NESO, licensed under the NESO Open Data Licence. Report a problem