Grid infrastructure › Connection queue › Onshore wind

ONSHORE WIND · SHET

Creag Riabhach Wind Farm

Creag Riabhach Wind Farm is a 105 MW onshore wind project in planning, connecting to the SSEN Transmission (north Scotland) network at Creag Riabhach 132/33kV Substation, with capacity due from July 2027. The connection agreement is held by Creag Riabhach Wind Farm Ltd.

Project stageIn planning
  1. Planning (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingFrom Jul 2027 (not yet reached)
  5. Closed (not yet reached)

Scoping and awaiting consents are both shown as planning. A connection agreement does not mean the project will be built: many queue projects never reach construction.

Connection details

NESO project number
PRO-000109-2
Customer
Creag Riabhach Wind Farm Ltd
Technology
Wind Onshore
Total capacity
105 MW
Change in this agreement
+13 MW
Capacity effective from
31 July 2027
Connection site
Creag Riabhach 132/33kV Substation
Transmission owner
SSEN Transmission (north Scotland)
Connection type
Direct connection to the transmission network
NESO project status
Scoping
Connections reform gate
Gate 1

Connection site

The connection site could not be placed on the map.

Projects connecting near Creag Riabhach · Grid map

Other projects at Creag Riabhach 132/33kV Substation

Source: NESO Transmission Entry Capacity (TEC) register, downloaded 8 November 2026. Contains data from NESO, licensed under the NESO Open Data Licence. Report a problem