NESO TEC REGISTER · GREAT BRITAIN

Grid connection projects in the connection queue

Every generator, battery and interconnector with an agreement to connect to the GB transmission network, from early scoping to built. Filter by technology, stage or network, and open a project for its connection details.

Projects shown1,590616.3 GW in total
In planning1,590scoping or awaiting consent
Consented or building265closest to connecting
Built400connected and operating

Map

Loading projects…

Voltage400 kV275 kV132 kVHVDCNew HVAC

ProjectsPlanningConsentedConstructionBuiltMajor project with its own page

Projects

1,590 projects · page 30 of 32
ProjectCapacityStageConnection siteFrom
Greenburn Wind & BESS
Wind + storage · Hm Gb (Wind) Ltd
50 MWScoping Coupar Angus 2 GSP
SSEN Transmission (north Scotland)
Oct 2031
Helen Street BESS
Battery storage · Vital Energi Solutions Limited
50 MWScoping Govan 132/33kV
SP Transmission (south Scotland)
Jun 2028
Iver
Battery storage · Juniper Energy Limited
50 MWScoping Iver 275kV Substation
National Grid (England & Wales)
Oct 2027
JBM Solar 13 - Melksham
Solar + storage · Jbm Solar Projects 13 Limited
50 MWScoping Melksham 400kV Substation
National Grid (England & Wales)
Jul 2026
Kearsley
Battery storage · Pivoted Power LLP
50 MWAwaiting Consents Kearsley 275kV Substation
National Grid (England & Wales)
Oct 2028
Kingsfold
Solar + storage · Greentech Projects Holding UK Limited
50 MWScoping Bolney GSP
National Grid (England & Wales)
Oct 2037
Laleham
Battery storage · Juniper Energy Limited
50 MWScoping Laleham 132kV Substation
National Grid (England & Wales)
May 2028
Land at Leitholm
Solar + storage · Noventum Power Solar 6 Limited
50 MWScoping Land At Leitholm 132Kv Substation
SP Transmission (south Scotland)
Jul 2031
Langbank Solar and BESS
Solar + storage · UK Renfrewshire 1 Ltd
50 MWScoping Langbank 132kV Substation
SP Transmission (south Scotland)
Oct 2027
Little Horsted
Solar + storage · Cse34 Limited
50 MWScoping Little Horsted GSP
National Grid (England & Wales)
Oct 2031
Lovedean Greener Grid Park
Battery storage · Statkraft UK Ltd
50 MWScoping Lovedean 400kV Substation
National Grid (England & Wales)
Jun 2028
Millennium East
Onshore wind · Renantis UK Limited
50 MWScoping FORT AUGUSTUS 2 400/33kV GRID SUPPLY POINT SUBSTATION
SSEN Transmission (north Scotland)
Oct 2035
Navas BESS
Battery storage · Opde UK Limited
50 MWScoping Lairg GSP
SSEN Transmission (north Scotland)
Oct 2033
Ninfield Greener Grid Park
Battery storage · Ninfield Grid Solutions Limited
50 MWAwaiting Consents Ninfield 400kV Substation
National Grid (England & Wales)
Jan 2031
NorthFleet Tertiary
Solar + storage · Cse29 Limited
50 MWScoping Northfleet East 400kV Substation
National Grid (England & Wales)
Jun 2028
Oldbury (Tertiary)
Battery storage · Pivoted Power LLP
50 MWAwaiting Consents Oldbury 275kV Substation
National Grid (England & Wales)
Jun 2027
Pitkerro Road
Battery storage · Vital Energi Solutions Limited
50 MWScoping Milton of Craigie GSP
SSEN Transmission (north Scotland)
Oct 2033
Provan Gas Works BESS
Battery storage · Vital Energi Solutions Limited
50 MWScoping Carntyne (SPD) GSP
SP Transmission (south Scotland)
Jun 2026
Scatsta Greener Grid Park
Battery storage · Statkraft Hydrogen UK Holding Limited
50 MWScoping Scatsta 132kV Substation
SSEN Transmission (north Scotland)
Oct 2028
Seabank (Tertiary)
Battery storage · Pivoted Power LLP
50 MWAwaiting Consents SEABANK 400/33kV SUBSTATION
National Grid (England & Wales)
Nov 2023
Sellindge (Tertiary)
Battery storage · Pivoted Power LLP
50 MWAwaiting Consents Sellindge 400kV Substation
National Grid (England & Wales)
Oct 2028
Spennymoor
Battery storage · Pivoted Power LLP
50 MWAwaiting Consents Spennymoor 400kV Substation
National Grid (England & Wales)
Oct 2028
Spennymoor PV & BESS
Solar + storage · Cse27 Limited
50 MWScoping Spennymoor 400kV Substation
National Grid (England & Wales)
Jul 2032
Spittal
Battery storage · Spittal Battery Storage Limited
50 MWScoping Mybster 2 132/33kV Substation
SSEN Transmission (north Scotland)
Oct 2030
STOR Field 9 BESS
Battery storage · Eku Energy Faune Projects (UK) Limited
50 MWScoping Inverkeithing GSP
SP Transmission (south Scotland)
Jul 2029
Swansea North
Battery storage · Edf Energy Renewables Limited
50 MWScoping Swansea North 400kV Substation
National Grid (England & Wales)
Jul 2028
Taigh an Uillt Energy Storage Park
Battery storage · Springbank Energy Storage Park Limited
50 MWScoping Ichrachan 132/33Kv Grid Supply Point Substation
SSEN Transmission (north Scotland)
Oct 2035
Taunton
Battery storage · Pivoted Power LLP
50 MWAwaiting Consents Taunton 400kV Substation
National Grid (England & Wales)
Oct 2031
Templeton BESS
Battery storage · Templeton Battery Storage Limited
50 MWScoping Lyndhurst 132/33kV
SSEN Transmission (north Scotland)
Oct 2031
Whitson
Battery storage · Pivoted Power LLP
50 MWScoping Whitson 275kV Substation
National Grid (England & Wales)
Oct 2027
Wright Street BESS
Battery storage · P3P Partners LLP
50 MWScoping Braehead Park 132/33kV
SP Transmission (south Scotland)
Oct 2025
Druim Leathann BEGA
Onshore wind · Druim Leathann Windfarm Limited
50 MWScoping Stornoway GSP
SSEN Transmission (north Scotland)
Mar 2027
Devonside BESS
Battery storage · Carlton Power Limited
50 MWScoping Devonside 132/33kV
SP Transmission (south Scotland)
Aug 2028
Lyndhurst Camperdown BESS
Battery storage · Geocore Ltd
50 MWScoping Charleston GSP 132/33kV
SSEN Transmission (north Scotland)
Oct 2031
Ochill BESS
Battery storage · Carlton Power Limited
50 MWScoping Ochill 132kV Substation
SP Transmission (south Scotland)
Aug 2028
Petre Street
Battery storage · Mercia Power Response Limited
50 MWScoping Pitsmoor GSP
National Grid (England & Wales)
Oct 2034
Sallachy Wind Farm
Onshore wind · Sallachy Wind Limited
50 MWAwaiting Consents Cassley GSP
SSEN Transmission (north Scotland)
Jul 2028
Shielburn Energy Park
Battery storage · Sunlaws Development Company Limited
50 MWScoping Fallago 400/33kV
SP Transmission (south Scotland)
Apr 2033
Arresgill Energy Storage 1
Battery storage · Arresgill Energy Storage 1 Limited
49 MWScoping Arresgill 132kV Substation
SP Transmission (south Scotland)
Oct 2031
Dougliehill BESS
Battery storage · Bluestone Energy Ltd
49 MWScoping Devol Moor 132/33Kv Grid Supply Point Substation
SP Transmission (south Scotland)
Oct 2026
Baillie Greener Grid Park
Battery storage · Statkraft UK Ltd
48 MWScoping Baillie 275KV Substation
SSEN Transmission (north Scotland)
Sep 2030
Bolney
Solar + storage · Pivoted Power LLP
48 MWScoping Bolney 400kV Substation
National Grid (England & Wales)
Jan 2031
Fleet Tertiary
Gas · Fleet Solar Limited
48 MWScoping Fleet 400kV Substation
National Grid (England & Wales)
Aug 2028
JBM Solar -Minety
Solar + storage · Jbm Solar Projects 14 Ltd
48 MWScoping Minety 400kV Substation
National Grid (England & Wales)
Nov 2028
Mannington
Solar + storage · Baywa R.e. UK Limited
48 MWScoping Mannington 400kV Substation
National Grid (England & Wales)
Apr 2028
NatPower Llanteg Green Energy Park
Battery storage · Np Spv 30 Limited
48 MWScoping South Wales West Connection Node C 400kV
National Grid (England & Wales)
Dec 2037
Southfields
Solar + storage · PD688IRO LTD
48 MWAwaiting Consents Minety 400kV Substation
National Grid (England & Wales)
Jun 2025
Willington East 1 (Tertiary)
Solar + storage · Enso Green Holdings U Limited
48 MWScoping Willington East 400kV Substation
National Grid (England & Wales)
Oct 2027
Willington East 2 (Tertiary)
Solar + storage · Enso Green Holdings Ss Limited
48 MWScoping Willington East 400kV Substation
National Grid (England & Wales)
Jul 2028
Lisa's Battery Storage
Battery storage · Potencia Energy Limited
47 MWAwaiting Consents Mybster 3 132/33kV Substation
SSEN Transmission (north Scotland)
Oct 2030
Page 30 of 32

Sources: NESO Transmission Entry Capacity (TEC) register and interconnector register (downloaded 8 November 2026); NESO Clean Power 2030 network map (existing and planned circuits, substations and network projects); National Grid Electricity Transmission overhead line routes. Contains data from NESO, licensed under the NESO Open Data Licence, and National Grid open data. Projects are placed at their connection substation, not the generating site; projects at new, unnamed “connection nodes” are listed but not mapped.