ONSHORE WIND · SHETMillennium East
Millennium East is a 50 MW onshore wind project in planning, connecting to the SSEN Transmission (north Scotland) network at FORT AUGUSTUS 2 400/33kV GRID SUPPLY POINT SUBSTATION, with capacity due from October 2035. The connection agreement is held by Renantis UK Limited.
- Planning (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingFrom Oct 2035 (not yet reached)
- Closed (not yet reached)
Scoping and awaiting consents are both shown as planning. A connection agreement does not mean the project will be built: many queue projects never reach construction.
Connection details
- NESO project number
- PRO-004010
- Customer
- Renantis UK Limited
- Technology
- Wind Onshore
- Total capacity
- 50 MW
- Change in this agreement
- +50 MW
- Capacity effective from
- 31 October 2035
- Connection site
- FORT AUGUSTUS 2 400/33kV GRID SUPPLY POINT SUBSTATION
- Transmission owner
- SSEN Transmission (north Scotland)
- Connection type
- Embedded (connects through the local distribution network)
- NESO project status
- Scoping
- Connections reform gate
- Gate 1
Connection site
The marker shows the connection substation, not the project itself, with the transmission network around it.