BATTERY STORAGE Β· SPT

Ochill BESS

Ochill BESS is a 50 MW battery storage project in planning, connecting to the SP Transmission (south Scotland) network at Ochill 132kV Substation, with capacity due from August 2028. The connection agreement is held by Carlton Power Limited.

Project stageIn planning
  1. Planning (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingFrom Aug 2028 (not yet reached)
  5. Closed (not yet reached)

Scoping and awaiting consents are both shown as planning. A connection agreement does not mean the project will be built: many queue projects never reach construction.

Connection details

NESO project number
PRO-002536
Customer
Carlton Power Limited
Technology
Energy Storage System
Total capacity
50 MW
Change in this agreement
+50 MW
Capacity effective from
18 August 2028
Connection site
Ochill 132kV Substation
Transmission owner
SP Transmission (south Scotland)
Connection type
Direct connection to the transmission network
NESO project status
Scoping