Grid infrastructure › Connection queue › Battery storage
BATTERY STORAGE · SHETBaillie Greener Grid Park
Baillie Greener Grid Park is a 48 MW battery storage project in planning, connecting to the SSEN Transmission (north Scotland) network at Baillie 275KV Substation, with capacity due from September 2030. The connection agreement is held by Statkraft UK Ltd.
- Planning (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingFrom Sep 2030 (not yet reached)
- Closed (not yet reached)
Scoping and awaiting consents are both shown as planning. A connection agreement does not mean the project will be built: many queue projects never reach construction.
Connection details
- NESO project number
- PRO-001701
- Customer
- Statkraft UK Ltd
- Technology
- Energy Storage System, Reactive Compensation
- Total capacity
- 48 MW
- Change in this agreement
- +48 MW
- Capacity effective from
- 30 September 2030
- Connection site
- Baillie 275KV Substation
- Transmission owner
- SSEN Transmission (north Scotland)
- Connection type
- Direct connection to the transmission network
- NESO project status
- Scoping
- Connections reform gate
- Gate 1
Connection site
The connection site could not be placed on the map.
Source: NESO Transmission Entry Capacity (TEC) register, downloaded 8 November 2026. Contains data from NESO, licensed under the NESO Open Data Licence. Report a problem