BATTERY STORAGE · SHET

Lisa's Battery Storage

Lisa's Battery Storage is a 47 MW battery storage project in planning, connecting to the SSEN Transmission (north Scotland) network at Mybster 3 132/33kV Substation, with capacity due from October 2030. The connection agreement is held by Potencia Energy Limited.

Project stageIn planning
  1. Planning (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingFrom Oct 2030 (not yet reached)
  5. Closed (not yet reached)

Scoping and awaiting consents are both shown as planning. A connection agreement does not mean the project will be built: many queue projects never reach construction.

Connection details

NESO project number
PRO-003280
Customer
Potencia Energy Limited
Technology
Energy Storage System
Total capacity
47 MW
Change in this agreement
+47 MW
Capacity effective from
31 October 2030
Connection site
Mybster 3 132/33kV Substation
Transmission owner
SSEN Transmission (north Scotland)
Connection type
Direct connection to the transmission network
NESO project status
Awaiting Consents

Connection site

The marker shows the connection substation, not the project itself, with the transmission network around it.

Projects connecting near Mybster · Grid map

Other projects at Mybster 3 132/33kV Substation

Source: NESO Transmission Entry Capacity (TEC) register, downloaded 8 November 2026. Contains data from NESO, licensed under the NESO Open Data Licence. Report a problem