BATTERY STORAGE Β· SPTProvan Gas Works BESS
Provan Gas Works BESS is a 50 MW battery storage project in planning, connecting to the SP Transmission (south Scotland) network at Carntyne (SPD) GSP, with capacity due from June 2026. The connection agreement is held by Vital Energi Solutions Limited.
- Planning (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingFrom Jun 2026 (not yet reached)
- Closed (not yet reached)
Scoping and awaiting consents are both shown as planning. A connection agreement does not mean the project will be built: many queue projects never reach construction.
Connection details
- NESO project number
- PRO-003179
- Customer
- Vital Energi Solutions Limited
- Technology
- Energy Storage System
- Total capacity
- 50 MW
- Change in this agreement
- +50 MW
- Capacity effective from
- 30 June 2026
- Connection site
- Carntyne (SPD) GSP
- Transmission owner
- SP Transmission (south Scotland)
- Connection type
- Embedded (connects through the local distribution network)
- NESO project status
- Scoping
- Connections reform gate
- Gate 1
Connection site
The marker shows the connection substation, not the project itself, with the transmission network around it.
Source: NESO Transmission Entry Capacity (TEC) register, downloaded 8 November 2026. Contains data from NESO, licensed under the NESO Open Data Licence. Report a problem