Wright Street BESS

Wright Street BESS is a 50 MW battery storage project in planning, connecting to the SP Transmission (south Scotland) network at Braehead Park 132/33kV, with capacity due from October 2025. The connection agreement is held by P3P Partners LLP.

Project stageIn planning
  1. Planning (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingFrom Oct 2025 (not yet reached)
  5. Closed (not yet reached)

Scoping and awaiting consents are both shown as planning. A connection agreement does not mean the project will be built: many queue projects never reach construction.

Connection details

NESO project number
PRO-003083
Customer
P3P Partners LLP
Technology
Energy Storage System
Total capacity
50 MW
Change in this agreement
+50 MW
Capacity effective from
31 October 2025
Connection site
Braehead Park 132/33kV
Transmission owner
SP Transmission (south Scotland)
Connection type
Embedded (connects through the local distribution network)
NESO project status
Scoping

Connection site

The marker shows the connection substation, not the project itself, with the transmission network around it.

Projects connecting near Braehead Park Β· Grid map

Other projects at Braehead Park 132/33kV