Withdrawn queue requests in Iowa

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown29566.1 GW
Active in queue23.9 GW123 requests
Agreement signed1,860 MW18 requests
Withdrawn29566.1 GW never built

Map

Loading requestsโ€ฆ
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

295 requests ยท page 1 of 6
ProjectCapacityStatusLocationRegionQueuedOnline
Other project PQ0002, Cerro Gordo County
Other
2,000 MWWithdrawn / abandoned Cerro Gordo, IAMISO Aug 2015target 2021
Onshore wind project T93, Pocahontas County
Onshore wind
1,500 MWWithdrawn / abandoned Pocahontas, IAPJM Oct 2007target 2010
Onshore wind project T92, Pocahontas County
Onshore wind
1,500 MWWithdrawn / abandoned Pocahontas, IAPJM Oct 2007target 2010
Onshore wind project J116, Hancock County
Onshore wind
999 MWWithdrawn / abandoned Hancock, IAMISO Feb 2010target 2013
Gas project E0025, Linn County
Gas ยท Interstate Power and Light Company (IPL)
987 MWWithdrawn / abandoned Linn, IAMISO Aug 2025target 2028
Coal project G718, Wapello County
Coal
900 MWWithdrawn / abandoned Wapello, IAMISO Dec 2006target 2009
Gas project J355, Adair County
Gas
810 MWWithdrawn / abandoned Adair, IAMISO May 2014target 2017
Gas project J363, Pottawattamie County
Gas
810 MWWithdrawn / abandoned Pottawattamie, IAMISO May 2014target 2016
Coal project G589, Black Hawk County
Coal
750 MWWithdrawn / abandoned Black Hawk, IAMISO Jan 2006target 2006
Linn County Generating Facility
Nuclear ยท NextEra Energy Resources Development, LLC
676 MWWithdrawn / abandoned Linn, IAMISO Aug 2025target 2028
Other project G220, Buchanan County
Other
650 MWWithdrawn / abandoned Buchanan, IAMISO Apr 2002target 2004
Gas project G219, Johnson County
Gas
650 MWWithdrawn / abandoned Johnson, IAMISO Apr 2002target 2006
Replace 15 MW of ALTW.FPL_DAEC Unit with Battery; Duane Arnold
Other
640 MWWithdrawn / abandoned Linn, IAMISO Sep 2021target 2023
Other project G129, Wapello County
Other
600 MWWithdrawn / abandoned Wapello, IAMISO Sep 2001target 2007
Gas project G181, Buchanan County
Gas
600 MWWithdrawn / abandoned Buchanan, IAMISO Mar 2002target 2004
Coal project G720, Marshall County
Coal
600 MWWithdrawn / abandoned Marshall, IAMISO Dec 2006target 2012
Gas project G182, Buchanan County
Gas
600 MWWithdrawn / abandoned Buchanan, IAMISO Mar 2002target 2004
Gas project G180, Marshall County
Gas
600 MWWithdrawn / abandoned Marshall, IAMISO Mar 2002target 2004
Other project G128, Marshall County
Other
600 MWWithdrawn / abandoned Marshall, IAMISO Sep 2001target 2003
Other project G127, Des Moines County
Other
600 MWWithdrawn / abandoned Des Moines, IAMISO Sep 2001target 2003
Gas project G179, Clinton County
Gas
600 MWWithdrawn / abandoned Clinton, IAMISO Mar 2002target 2002
Other project G178, Clinton County
Other
600 MWWithdrawn / abandoned Clinton, IAMISO Mar 2002target 2003
Other project G187, Muscatine County
Other
600 MWWithdrawn / abandoned Muscatine, IAMISO Apr 2002target 2003
Coal project G719, Wapello County
Coal
600 MWWithdrawn / abandoned Wapello, IAMISO Dec 2006target 2010
Onshore wind project J462, Emmet County
Onshore wind
598 MWWithdrawn / abandoned Emmet, IAMISO May 2015target 2016
Gas project G174, Cerro Gordo County
Gas
550 MWWithdrawn / abandoned Cerro Gordo, IAMISO Feb 2002target 2003
Onshore wind project R50, Washington County
Onshore wind
501 MWWithdrawn / abandoned Washington, IAMISO Feb 2008target 2010
Onshore wind project G973, Washington County
Onshore wind
501 MWWithdrawn / abandoned Washington, IAMISO Feb 2008target 2011
Other project G158, Linn County
Other
500 MWWithdrawn / abandoned Linn, IAMISO Nov 2001target 2003
Onshore wind project J439, Emmet County
Onshore wind
500 MWWithdrawn / abandoned Emmet, IAMISO Mar 2015target 2016
Other project G156, Cerro Gordo County
Other
500 MWWithdrawn / abandoned Cerro Gordo, IAMISO Nov 2001target 2005
Onshore wind project J154, Washington County
Onshore wind
500 MWWithdrawn / abandoned Washington, IAMISO Jun 2010target 2011
Other project G157, Linn County
Other
500 MWWithdrawn / abandoned Linn, IAMISO Nov 2001target 2003
Onshore wind project J192, Washington County
Onshore wind
500 MWWithdrawn / abandoned Washington, IAMISO Jan 2011target 2012
Other project G159, Buchanan County
Other
500 MWWithdrawn / abandoned Buchanan, IAMISO Nov 2001target 2003
Onshore wind project R52, Adair County
Onshore wind
500 MWWithdrawn / abandoned Adair, IAMISO Mar 2008target 2010
Onshore wind project J501, Hancock County
Onshore wind
500 MWWithdrawn / abandoned Hancock, IAMISO Nov 2015target 2017
Gas project J364, Adair County
Gas
464 MWWithdrawn / abandoned Adair, IAMISO May 2014target 2016
Gas project J365, Pottawattamie County
Gas
464 MWWithdrawn / abandoned Pottawattamie, IAMISO May 2014target 2018
Solar project J3998, Cerro Gordo County
Solar
450 MWWithdrawn / abandoned Cerro Gordo, IAMISO Feb 2025target 2030
Onshore wind project J578, Audubon County
Onshore wind
400 MWWithdrawn / abandoned Audubon, IAMISO May 2016target 2018
Onshore wind project J1427, Benton County
Onshore wind
400 MWWithdrawn / abandoned Benton, IAMISO Apr 2019target 2022
Onshore wind project G972, Fayette County
Onshore wind
400 MWWithdrawn / abandoned Fayette, IAMISO Feb 2008target 2010
Battery storage project J3022, Taylor County
Battery storage
400 MWWithdrawn / abandoned Taylor, IAMISO Sep 2022target 2026
Onshore wind project J1341, Buchanan County
Onshore wind
398 MWWithdrawn / abandoned Buchanan, IAMISO Apr 2019target 2022
Other project G126, Des Moines County
Other
325 MWWithdrawn / abandoned Des Moines, IAMISO Sep 2001
Other project G125, Clinton County
Other
325 MWWithdrawn / abandoned Clinton, IAMISO Sep 2001
Onshore wind project J342, Buchanan County
Onshore wind
305 MWWithdrawn / abandoned Buchanan, IAMISO May 2014target 2015
Onshore wind project J2481, Pocahontas County
Onshore wind
300 MWWithdrawn / abandoned Pocahontas, IAMISO Sep 2022target 2030
Onshore wind project J410, Fayette County
Onshore wind
300 MWWithdrawn / abandoned Fayette, IAMISO Nov 2014target 2016
Page 1 of 6

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines ยท Planned power plants (EIA)