๐Ÿ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more โ†’ Skip to main content

United States โ€บ Grid โ€บ Interconnection queues โ€บ Illinois

OCTARY USA ยท INTERCONNECTION QUEUES

Onshore wind interconnection queue in Illinois

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown7615.5 GW
Active in queue15.5 GW76 requests
Agreement signed2,606 MW10 requests
Withdrawn23940.4 GW never built

Map

Loading requestsโ€ฆ
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

76 requests ยท page 1 of 2
ProjectCapacityStatusLocationRegionQueuedOnline
Heritage Prairie Wind
Onshore wind
850 MWAgreement signed Kankakee, ILPJM Sep 2017target 2028
Onshore wind project J3860, Peoria County
Onshore wind
500 MWIn study Peoria, ILMISO Jan 2025target 2030
Onshore wind project J3730, Macoupin County
Onshore wind
444 MWIn study Macoupin, ILMISO Apr 2024target 2028
Onshore wind project J3712, Peoria County
Onshore wind
400 MWIn study Peoria, ILMISO Apr 2024target 2028
Onshore wind project J3521, Shelby County
Onshore wind
350 MWIn study Shelby, ILMISO Apr 2024target 2028
Panther Grove Wind
Onshore wind
350 MWAgreement signed Woodford, ILPJM Sep 2018target 2027
Onshore wind project J3991, Mclean County
Onshore wind
340 MWIn study Mclean, ILMISO Apr 2025target 2029
Onshore wind project J844, Knox County
Onshore wind
300 MWUnder construction Knox, ILMISO Jun 2017target 2021
Onshore wind project AH2-270, Whiteside County
Onshore wind
300 MWIn study Whiteside, ILPJM Mar 2022target 2026
Onshore wind project J3699, Henry County
Onshore wind
300 MWIn study Henry, ILMISO Apr 2024target 2028
Onshore wind project J3901, Shelby County
Onshore wind
300 MWIn study Shelby, ILMISO Jan 2025target 2030
Onshore wind project J1360, Piatt County
Onshore wind
300 MWAgreement signed Piatt, ILMISO Apr 2019target 2024
Onshore wind project J3681, Mclean County
Onshore wind
300 MWIn study Mclean, ILMISO Apr 2024target 2028
Panther Grove 2
Onshore wind
300 MWAgreement signed Woodford, ILPJM Sep 2018target 2028
Onshore wind project J3853, Iroquois County
Onshore wind
300 MWIn study Iroquois, ILMISO Dec 2024target 2029
Onshore wind project J4112, Rock Island County
Onshore wind
300 MWIn study Rock Island, ILMISO Oct 2025target 2030
Livingston Wind
Onshore wind ยท Livingston Wind Project, LLC
255 MWIn study Livingston, ILPJM Sep 2018target 2021
Onshore wind project J3078, Peoria County
Onshore wind
252 MWIn study Peoria, ILMISO Sep 2022target 2026
Onshore wind project J848, Christian County
Onshore wind
250 MWUnder construction Christian, ILMISO Jun 2017target 2021
Onshore wind project J3750, Mercer County
Onshore wind
250 MWIn study Mercer, ILMISO Apr 2024target 2028
Onshore wind project J2275, Peoria County
Onshore wind
250 MWIn study Peoria, ILMISO Mar 2022target 2025
Onshore wind project J4018, Ford County
Onshore wind
250 MWIn study Ford, ILMISO May 2025target 2029
Onshore wind project J3856, Wabash County
Onshore wind
235 MWIn study Wabash, ILMISO Dec 2024target 2030
Onshore wind project J3830
Onshore wind
225 MWIn study ILMISO Apr 2024target 2028
Onshore wind project J3391, Coles County
Onshore wind
200 MWIn study Coles, ILMISO Apr 2024target 2027
Onshore wind project J3907, Stark County
Onshore wind
200 MWIn study Stark, ILMISO Mar 2025target 2030
Onshore wind project J1289, Morgan County
Onshore wind
200 MWAgreement signed Morgan, ILMISO Apr 2019target 2024
Onshore wind project J2049, Shelby County
Onshore wind
200 MWIn study Shelby, ILMISO Mar 2022target 2025
Onshore wind project J1831, Menard County
Onshore wind
200 MWIn study Menard, ILMISO Jun 2020target 2026
Onshore wind project J1115, Macon County
Onshore wind
200 MWUnder construction Macon, ILMISO Mar 2018target 2024
Onshore wind project J1701, Mcdonough County
Onshore wind
200 MWIn study Mcdonough, ILMISO Dec 2021target 2026
Onshore wind project J2614, Henry County
Onshore wind
200 MWIn study Henry, ILMISO Sep 2022target 2026
Onshore wind project J1926, Tazewell County
Onshore wind
200 MWIn study Tazewell, ILMISO Mar 2022target 2025
Onshore wind project J3338, Hamilton County
Onshore wind
200 MWIn study Hamilton, ILMISO Apr 2024target 2028
Onshore wind project J3493, Mcdonough County
Onshore wind
200 MWIn study Mcdonough, ILMISO Apr 2024target 2028
Onshore wind project J2938, Knox County
Onshore wind
200 MWIn study Knox, ILMISO Sep 2022target 2025
Onshore wind project AI1-191, Stephenson County
Onshore wind
200 MWIn study Stephenson, ILPJM Sep 2022target 2027
Rolling Farms Wind Project
Onshore wind
200 MWAgreement signed Christian, ILPJM Aug 2019target 2029
Onshore wind project J2963, Mason County
Onshore wind
200 MWIn study Mason, ILMISO Sep 2022target 2025
Lower Crossing Wind
Onshore wind
200 MWPaused / redesign Kankakee, ILPJM Jan 2018target 2026
Onshore wind project J3519, Mason County
Onshore wind
200 MWIn study Mason, ILMISO Apr 2024target 2028
Onshore wind project J3566, Mclean County
Onshore wind
198 MWIn study Mclean, ILMISO Apr 2024target 2028
Onshore wind project J3753, Iroquois County
Onshore wind
196 MWIn study Iroquois, ILMISO Apr 2024target 2028
Gipper Wind Farm
Onshore wind ยท Gipper Wind Farm, LLC
191 MWIn study Whiteside, ILPJM Sep 2019target 2022
Onshore wind project J2247, Marshall County
Onshore wind
178 MWIn study Marshall, ILMISO Mar 2022target 2024
Onshore wind project J3905, Tazewell County
Onshore wind
175 MWIn study Tazewell, ILMISO Mar 2025target 2030
Onshore wind project J1967, Champaign County
Onshore wind
150 MWIn study Champaign, ILMISO Mar 2022target 2025
Bright Stalk Generating Facility
Onshore wind ยท Lexington Chenoa Wind Farm LLC
150 MWIn study Mclean, ILPJM Mar 2019target 2022
Osagrove Flats Wind
Onshore wind
150 MWAgreement signed Lasalle, ILPJM Jan 2018target 2026
Leaf River Wind
Onshore wind ยท Leaf River Wind, LLC
150 MWIn study Ogle, ILPJM Sep 2018target 2021
Page 1 of 2

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines ยท Planned power plants (EIA)