United States › Grid › Interconnection queues › Illinois
ONSHORE WIND · PJMOnshore wind project AI1-191, Stephenson County
Onshore wind project AI1-191, Stephenson County is a 200 MW onshore wind request in interconnection study in the PJM interconnection queue, in Stephenson County, Illinois, connecting to ComEd.
Queue statusIn planning
- PlanningQueued Sep 2022 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Dec 2027 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- AI1-191
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- ComEd
- Connection point (POI)
- Landcaster - Pecatonica 138 kV
- Location
- Stephenson County, Illinois
- Technology
- Wind: 200 MW
- Total requested
- 200 MW
- Service type
- Network resource (NRIS)
- Study phase
- Feasibility Study
- Queue status
- Active
- Entered queue
- 9 September 2022
- Proposed online date
- December 2027
Location
Marker shows the centre of Stephenson County; the queue data does not give exact sites.
Other requests in Stephenson County
- Battery storage project AH2-204, Stephenson CountyBattery storage · 170 MW · in study
- Solar + storage project AI1-174, Stephenson CountySolar + storage · 118 MW · in study
- Battery storage project AH2-375, Stephenson CountyBattery storage · 106 MW · in study
- Battery storage project AH2-372, Stephenson CountyBattery storage · 52.0 MW · in study
- Solar project AI1-173, Stephenson CountySolar · 16.0 MW · in study
- High Point II SolarSolar · 50.0 MW · built
- High Point SolarSolar · 50.0 MW · built
- Onshore wind project AF1-314, Stephenson CountyOnshore wind · 212 MW · withdrawn
- Onshore wind project AF2-267, Stephenson CountyOnshore wind · 211 MW · withdrawn
- Onshore wind project R96, Stephenson CountyOnshore wind · 200 MW · withdrawn
- Onshore wind project R64, Stephenson CountyOnshore wind · 200 MW · withdrawn
- Onshore wind project U2-003, Stephenson CountyOnshore wind · 200 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem