United States βΊ Grid βΊ Interconnection queues βΊ Illinois
ONSHORE WIND Β· MISOOnshore wind project J3830
Onshore wind project J3830 is a 225 MW onshore wind request in interconnection study in the MISO interconnection queue, connecting to AMEREN ILLINOIS.
Queue statusIn planning
- PlanningQueued Apr 2024 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Jun 2028 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- J3830
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- AMEREN ILLINOIS
- Connection point (POI)
- Other_
- Location
- Illinois
- Technology
- Wind: 225 MW
- Total requested
- 225 MW
- Service type
- Network resource (NRIS)
- Study phase
- Study Phase: DPP 1
- Queue status
- Active
- Entered queue
- 16 April 2024
- Proposed online date
- June 2028
Location
No county location in the queue data.
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem