Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown10240.9 GW
Active in queue20.2 GW33 requests
Agreement signed17.3 GW29 requests
Withdrawn10240.9 GW never built

Map

Loading requestsโ€ฆ
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

102 requests ยท page 1 of 3
ProjectCapacityStatusLocationRegionQueuedOnline
Pinebrook Solar Hybrid Energy Center
Solar + storage
3,074 MWWithdrawn / abandoned Fresno, CACAISO Apr 2019target 2024
Nimitz 2 Generation
Wind + storage
1,887 MWWithdrawn / abandoned San Luis Obispo, CACAISO Apr 2019target 2026
Nimitz 1 Generation
Wind + storage
1,887 MWWithdrawn / abandoned San Luis Obispo, CACAISO Apr 2019target 2024
Tempest Generation
Wind + storage
1,887 MWWithdrawn / abandoned Humboldt, CACAISO Apr 2019target 2025
Seawolf Generation
Wind + storage
1,887 MWWithdrawn / abandoned San Luis Obispo, CACAISO Apr 2019target 2024
Una Lake Solar
Solar + storage
1,243 MWWithdrawn / abandoned Los Angeles, CACAISO Apr 2019target 2022
Las Brisas Offshore Wind
Offshore wind
1,188 MWWithdrawn / abandoned San Luis Obispo, CACAISO Apr 2019target 2026
Solo
Solar + storage
1,037 MWWithdrawn / abandoned Riverside, CACAISO Apr 2019target 2022
Sunnynook Solar Center
Solar + storage
1,029 MWWithdrawn / abandoned Riverside, CACAISO Apr 2019target 2026
Oatfield Hybrid Solar
Solar + storage
1,000 MWWithdrawn / abandoned Kings, CACAISO Apr 2019target 2022
Yeager Hybrid Solar
Solar + storage
813 MWWithdrawn / abandoned Kern, CACAISO Apr 2019target 2022
Bradmoor Solar
Solar + storage
719 MWWithdrawn / abandoned Solano, CACAISO Apr 2019target 2022
Bright Star Hybrid
Solar + storage
719 MWWithdrawn / abandoned San Joaquin, CACAISO Apr 2019target 2022
Steel City Energy Storage
Battery storage
650 MWWithdrawn / abandoned Contra Costa, CACAISO Apr 2019target 2025
Ventus Renewable Energy Center
Other
643 MWWithdrawn / abandoned Riverside, CACAISO Apr 2019target 2023
Salton Solar
Solar + storage
632 MWWithdrawn / abandoned Imperial, CACAISO Apr 2019target 2023
Lion Rock Offshore Wind
Offshore wind
627 MWWithdrawn / abandoned San Luis Obispo, CACAISO Apr 2019target 2026
Fort Tejon Solar
Solar + storage
617 MWWithdrawn / abandoned Los Angeles, CACAISO Apr 2019target 2026
Grand Lake Hybrid Solar
Solar + storage
504 MWWithdrawn / abandoned Kings, CACAISO Apr 2019target 2023
Solar + storage project Q70, Kern County
Solar + storage
500 MWWithdrawn / abandoned Kern, CAWest May 2019target 2022
SV Energy Storage Facility
Battery storage
500 MWWithdrawn / abandoned San Diego, CACAISO Apr 2019target 2026
Fokus Renewable Energy Center
Other
472 MWWithdrawn / abandoned Kern, CACAISO Apr 2019target 2023
Big Duck Storage
Battery storage
462 MWWithdrawn / abandoned Fresno, CACAISO Apr 2019target 2022
Ranchero Solar
Solar + storage
450 MWWithdrawn / abandoned Colusa, CACAISO Apr 2019target 2023
Triumph Solar
Solar + storage
450 MWWithdrawn / abandoned Tulare, CACAISO Apr 2019target 2023
Trestles Energy Storage
Battery storage
434 MWWithdrawn / abandoned Los Angeles, CACAISO Apr 2019target 2022
Boulder Oaks Hybrid
Wind + storage
411 MWWithdrawn / abandoned San Diego, CACAISO Apr 2019target 2023
Doradus
Solar + storage
406 MWWithdrawn / abandoned Kern, CACAISO Apr 2019target 2022
Rigal
Solar + storage
406 MWWithdrawn / abandoned Kern, CACAISO Apr 2019target 2022
Ash Tree Hybrid Solar
Solar + storage
406 MWWithdrawn / abandoned Fresno, CACAISO Apr 2019target 2022
Familia Hybrid Solar
Solar + storage
405 MWWithdrawn / abandoned Maricopa, CACAISO Apr 2019target 2022
Garces Hybrid Solar
Solar + storage
403 MWWithdrawn / abandoned Kern, CACAISO Apr 2019target 2022
Agua Amarga Wind
Onshore wind
403 MWWithdrawn / abandoned San Luis Obispo, CACAISO Apr 2019target 2023
DRY Grape Hybrid Solar
Solar + storage
403 MWWithdrawn / abandoned Fresno, CACAISO Apr 2019target 2022
Yellow Hay Hybrid Solar
Solar + storage
400 MWWithdrawn / abandoned Tulare, CACAISO Apr 2019target 2022
Solar + storage project Q72, San Bernardino County
Solar + storage
400 MWWithdrawn / abandoned San Bernardino, CAWest Jul 2019target 2021
Solar project 2, Sacramento County
Solar
400 MWWithdrawn / abandoned Sacramento, CAWest Oct 2019target 2023
Draco Solar
Solar + storage
375 MWWithdrawn / abandoned Kern, CACAISO Apr 2019target 2023
Peony
Solar
359 MWWithdrawn / abandoned Kern, CACAISO Apr 2019target 2022
Journey Storage
Battery storage
355 MWWithdrawn / abandoned Kings, CACAISO Apr 2019target 2022
Barrenspring
Solar + storage
308 MWWithdrawn / abandoned Tulare, CACAISO Apr 2019target 2023
Vestal Valley
Solar + storage
308 MWWithdrawn / abandoned Tulare, CACAISO Apr 2019target 2023
San Bernardino BESS
Battery storage
308 MWWithdrawn / abandoned San Bernardino, CACAISO Apr 2019target 2022
Hinson BESS
Battery storage
308 MWWithdrawn / abandoned Los Angeles, CACAISO Apr 2019target 2022
Nikola Norte
Solar + storage
306 MWWithdrawn / abandoned San Joaquin, CACAISO Apr 2019target 2023
Tesoster
Solar + storage
306 MWWithdrawn / abandoned San Joaquin, CACAISO Apr 2019target 2023
Nikovaster
Solar + storage
306 MWWithdrawn / abandoned Stanislaus, CACAISO Apr 2019target 2023
Superba Storage 1
Battery storage
305 MWWithdrawn / abandoned Orange, CACAISO Apr 2019target 2021
Arcturus
Solar + storage
304 MWWithdrawn / abandoned Kern, CACAISO Apr 2019target 2026
Sugarloaf Hybrid Solar
Solar + storage
303 MWWithdrawn / abandoned Fresno, CACAISO Apr 2019target 2022
Page 1 of 3

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines ยท Planned power plants (EIA)