United States › Grid › Interconnection queues › California

BATTERY STORAGE · CAISO

Hinson BESS

Hinson BESS is a 308 MW battery storage request withdrawn in the CAISO interconnection queue, in Los Angeles County, California, connecting to SCE.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Apr 2019 (completed)
  2. Withdrawn / abandonedApr 2020 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
1609
Grid region
CAISO (California)
Utility / transmission owner
SCE
Connection point (POI)
Hinson Substation 220kV
Location
Los Angeles County, California
Technology
Battery: 308 MW
Total requested
308 MW
Service type
Network resource (NRIS)
Study phase
System Impact Study
Queue status
Withdrawn
Entered queue
15 April 2019
Proposed online date
August 2022
Withdrawn
April 2020

Location

Marker shows the centre of Los Angeles County; the queue data does not give exact sites.

Power plants in California · Transmission lines in California

Other requests in Los Angeles County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem