United States › Grid › Interconnection queues › California

SOLAR + STORAGE · CAISO

Pinebrook Solar Hybrid Energy Center

Pinebrook Solar Hybrid Energy Center is a 3,074 MW solar + storage request withdrawn in the CAISO interconnection queue, in Fresno County, California, connecting to PGAE.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Apr 2019 (completed)
  2. Withdrawn / abandonedApr 2020 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
1581
Grid region
CAISO (California)
Utility / transmission owner
PGAE
Connection point (POI)
Los Banos-Gates #1 500 kV
Location
Fresno County, California
Technology
Solar: 1,537 MW · Battery: 1,537 MW
Total requested
3,074 MW
Service type
Network resource (NRIS)
Study phase
System Impact Study
Queue status
Withdrawn
Entered queue
15 April 2019
Proposed online date
November 2024
Withdrawn
April 2020

Location

Marker shows the centre of Fresno County; the queue data does not give exact sites.

Power plants in California · Transmission lines in California

Other requests in Fresno County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem