Big Duck Storage

Big Duck Storage is a 462 MW battery storage request withdrawn in the CAISO interconnection queue, in Fresno County, California, connecting to PGAE.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Apr 2019 (completed)
  2. Withdrawn / abandonedFeb 2020 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
1574
Grid region
CAISO (California)
Utility / transmission owner
PGAE
Connection point (POI)
Panoche Substation 230 kV
Location
Fresno County, California
Technology
Battery: 462 MW
Total requested
462 MW
Service type
Network resource (NRIS)
Study phase
System Impact Study
Queue status
Withdrawn
Entered queue
15 April 2019
Proposed online date
July 2022
Withdrawn
February 2020

Location

Marker shows the centre of Fresno County; the queue data does not give exact sites.

Power plants in California · Transmission lines in California

Other requests in Fresno County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem