Lion Rock Offshore Wind

Lion Rock Offshore Wind is a 627 MW offshore wind request withdrawn in the CAISO interconnection queue, in San Luis Obispo County, California, connecting to PGAE.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Apr 2019 (completed)
  2. Withdrawn / abandonedApr 2020 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
1599
Grid region
CAISO (California)
Utility / transmission owner
PGAE
Connection point (POI)
Morro Bay Substation 230kV
Location
San Luis Obispo County, California
Technology
Offshore Wind: 627 MW
Total requested
627 MW
Service type
Network resource (NRIS)
Study phase
System Impact Study
Queue status
Withdrawn
Entered queue
15 April 2019
Proposed online date
April 2026
Withdrawn
April 2020

Location

Marker shows the centre of San Luis Obispo County; the queue data does not give exact sites.

Power plants in California · Transmission lines in California

Other requests in San Luis Obispo County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem