SOLAR + STORAGE · CAISO

Fort Tejon Solar

Fort Tejon Solar is a 617 MW solar + storage request withdrawn in the CAISO interconnection queue, in Los Angeles County, California, connecting to SCE.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Apr 2019 (completed)
  2. Withdrawn / abandonedMay 2021 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
1628
Grid region
CAISO (California)
Utility / transmission owner
SCE
Connection point (POI)
Vincent Substation 230kV
Location
Los Angeles County, California
Technology
Solar: 310 MW · Battery: 306 MW
Total requested
617 MW
Service type
Network resource (NRIS)
Study phase
System Impact Study
Queue status
Withdrawn
Entered queue
15 April 2019
Proposed online date
August 2026
Withdrawn
May 2021

Location

Marker shows the centre of Los Angeles County; the queue data does not give exact sites.

Power plants in California · Transmission lines in California

Other requests in Los Angeles County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem