SOLAR + STORAGE · CAISO

Oatfield Hybrid Solar

Oatfield Hybrid Solar is a 1,000 MW solar + storage request withdrawn in the CAISO interconnection queue, in Kings County, California, connecting to PGAE.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Apr 2019 (completed)
  2. Withdrawn / abandonedMar 2020 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
1592
Grid region
CAISO (California)
Utility / transmission owner
PGAE
Connection point (POI)
Gates-Templeton 230 kV
Location
Kings County, California
Technology
Solar: 500 MW · Battery: 500 MW
Total requested
1,000 MW
Service type
Network resource (NRIS)
Study phase
System Impact Study
Queue status
Withdrawn
Entered queue
15 April 2019
Proposed online date
November 2022
Withdrawn
March 2020

Location

Marker shows the centre of Kings County; the queue data does not give exact sites.