United States › Grid › Interconnection queues › California

SOLAR + STORAGE · CAISO

Tesoster

Tesoster is a 306 MW solar + storage request withdrawn in the CAISO interconnection queue, in San Joaquin County, California, connecting to PGAE.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Apr 2019 (completed)
  2. Withdrawn / abandonedFeb 2020 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
1561
Grid region
CAISO (California)
Utility / transmission owner
PGAE
Connection point (POI)
Tesla-Weber 230kV
Location
San Joaquin County, California
Technology
Solar: 244 MW · Battery: 61.3 MW
Total requested
306 MW
Service type
Network resource (NRIS)
Study phase
System Impact Study
Queue status
Withdrawn
Entered queue
15 April 2019
Proposed online date
April 2023
Withdrawn
February 2020

Location

Marker shows the centre of San Joaquin County; the queue data does not give exact sites.

Power plants in California · Transmission lines in California

Other requests in San Joaquin County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem