United States › Grid › Interconnection queues › California

BATTERY STORAGE · CAISO

Pathfinder Storage

Pathfinder Storage is a 268 MW battery storage request with a signed interconnection agreement in the CAISO interconnection queue, in San Joaquin County, California, connecting to PGAE.

Queue statusConsented
  1. PlanningQueued Apr 2021 (completed)
  2. ConsentedDec 2024 (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Jun 2031 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
1896
Grid region
CAISO (California)
Utility / transmission owner
PGAE
Connection point (POI)
Weber 60 kV
Location
San Joaquin County, California
Technology
Battery: 268 MW
Total requested
268 MW
Service type
Network resource (NRIS)
Study phase
Executed
Queue status
Active
Entered queue
15 April 2021
Agreement signed
17 December 2024
Proposed online date
June 2031

Location

Marker shows the centre of San Joaquin County; the queue data does not give exact sites.

Power plants in California · Transmission lines in California

Other requests in San Joaquin County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem