Tracy Combined-Cycle Power Plant

Tracy Combined-Cycle Power Plant is a 185 MW gas request with a signed interconnection agreement in the CAISO interconnection queue, in San Joaquin County, California, connecting to PGAE.

Queue statusConsented
  1. PlanningQueued Oct 2007 (completed)
  2. ConsentedMay 2010 (current stage)
  3. Construction (not yet reached)
  4. OperatingMay 2012 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
268
Grid region
CAISO (California)
Utility / transmission owner
PGAE
Connection point (POI)
Tesla-Manteca 115kV line via Schulte Switchyard
Location
San Joaquin County, California
Technology
Gas: 145 MW · Battery: 40.0 MW
Total requested
185 MW
Service type
Network resource (NRIS)
Study phase
Executed
Queue status
Active
Entered queue
24 October 2007
Agreement signed
24 May 2010
Proposed online date
April 2027
Came online
May 2012

Location

Marker shows the centre of San Joaquin County; the queue data does not give exact sites.

Power plants in California · Transmission lines in California

Other requests in San Joaquin County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem