United States βΊ Grid βΊ Interconnection queues βΊ South Dakota
OCTARY USA Β· INTERCONNECTION QUEUESWithdrawn queue requests in South Dakota, MISO
Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.
Map
Requests
| Project | Capacity | Status |
|---|---|---|
| Onshore wind project G705, Hand County Onshore wind |
2,000 MW | Withdrawn / abandoned |
| Onshore wind project G703, Hand County Onshore wind |
1,500 MW | Withdrawn / abandoned |
| Onshore wind project G704, Hand County Onshore wind |
1,500 MW | Withdrawn / abandoned |
| Onshore wind project G884, Roberts County Onshore wind |
1,500 MW | Withdrawn / abandoned |
| Onshore wind project G731, Jerauld County Onshore wind |
750 MW | Withdrawn / abandoned |
| Other project G118, Grant County Other |
650 MW | Withdrawn / abandoned |
| Coal project G392, Grant County Coal |
600 MW | Withdrawn / abandoned |
| Onshore wind project H095, Roberts County Onshore wind |
550 MW | Withdrawn / abandoned |
| Onshore wind project J4135, Grant County Onshore wind |
450 MW | Withdrawn / abandoned |
| Gas project J4032, Deuel County Gas |
442 MW | Withdrawn / abandoned |
| Onshore wind project J1621, Mcpherson County Onshore wind |
400 MW | Withdrawn / abandoned |
| Onshore wind project J744, Lincoln County Onshore wind |
400 MW | Withdrawn / abandoned |
| Onshore wind project J773, Codington County Onshore wind |
400 MW | Withdrawn / abandoned |
| Onshore wind project J151, Moody County Onshore wind |
350 MW | Withdrawn / abandoned |
| Onshore wind project J3279, Day County Onshore wind |
300 MW | Withdrawn / abandoned |
| Onshore wind project J597, Deuel County Onshore wind |
300 MW | Withdrawn / abandoned |
| Onshore wind project G982, Roberts County Onshore wind |
300 MW | Withdrawn / abandoned |
| Battery storage project J4136, Grant County Battery storage |
250 MW | Withdrawn / abandoned |
| Onshore wind project G699, Roberts County Onshore wind |
250 MW | Withdrawn / abandoned |
| Onshore wind project G939, Grant County Onshore wind |
250 MW | Withdrawn / abandoned |
| Onshore wind project G804, Deuel County Onshore wind |
250 MW | Withdrawn / abandoned |
| Onshore wind project G722, Grant County Onshore wind |
250 MW | Withdrawn / abandoned |
| Battery storage project J3824, Roberts County Battery storage |
250 MW | Withdrawn / abandoned |
| Solar project J3862, Deuel County Solar |
250 MW | Withdrawn / abandoned |
| Onshore wind project J1989, Brown County Onshore wind |
250 MW | Withdrawn / abandoned |
| Onshore wind project G764, Minnehaha County Onshore wind |
242 MW | Withdrawn / abandoned |
| Gas project G765, Brookings County Gas |
240 MW | Withdrawn / abandoned |
| Onshore wind project J638, Deuel County Onshore wind |
204 MW | Withdrawn / abandoned |
| Onshore wind project J266, Roberts County Onshore wind |
200 MW | Withdrawn / abandoned |
| Onshore wind project H016, Minnehaha County Onshore wind |
200 MW | Withdrawn / abandoned |
| Onshore wind project H025, Minnehaha County Onshore wind |
200 MW | Withdrawn / abandoned |
| Onshore wind project J1594, Clark County Onshore wind |
200 MW | Withdrawn / abandoned |
| Onshore wind project J2338, Mcpherson County Onshore wind |
200 MW | Withdrawn / abandoned |
| Onshore wind project J133, Codington County Onshore wind |
200 MW | Withdrawn / abandoned |
| Onshore wind project J933, Day County Onshore wind |
200 MW | Withdrawn / abandoned |
| Onshore wind project J721, Codington County Onshore wind |
200 MW | Withdrawn / abandoned |
| Onshore wind project J2333, Mcpherson County Onshore wind |
200 MW | Withdrawn / abandoned |
| Onshore wind project J629, Deuel County Onshore wind |
200 MW | Withdrawn / abandoned |
| Onshore wind project J747, Deuel County Onshore wind |
200 MW | Withdrawn / abandoned |
| Onshore wind project J458, Clark County Onshore wind |
200 MW | Withdrawn / abandoned |
| Onshore wind project J774, Codington County Onshore wind |
200 MW | Withdrawn / abandoned |
| Onshore wind project J630, Deuel County Onshore wind |
200 MW | Withdrawn / abandoned |
| Onshore wind project J941, Grant County Onshore wind |
200 MW | Withdrawn / abandoned |
| Onshore wind project J599, Walworth County Onshore wind |
200 MW | Withdrawn / abandoned |
| Onshore wind project J459, Grant County Onshore wind |
200 MW | Withdrawn / abandoned |
| Onshore wind project J189, Minnehaha County Onshore wind |
200 MW | Withdrawn / abandoned |
| Onshore wind project G776, Brookings County Onshore wind |
200 MW | Withdrawn / abandoned |
| Onshore wind project J775, Codington County Onshore wind |
200 MW | Withdrawn / abandoned |
| Onshore wind project J080, Brookings County Onshore wind |
200 MW | Withdrawn / abandoned |
| Onshore wind project J1521, Day County Onshore wind |
200 MW | Withdrawn / abandoned |
Capacity in the queue by state
Click a state to drill down.
By grid region
ISO/RTO markets and the non-ISO West and Southeast.
- MISO (Midcontinent)91 Β· 23.6 GW
- West (non-ISO utilities)100 Β· 22.1 GW
- SPP (Southwest Power Pool)55 Β· 9,641 MW
- PJM (Mid-Atlantic, Midwest)3 Β· 5,000 MW
Requests by year joined
Capacity of requests in this view, by the year they entered the queue. Click a year.
Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)