United States β€Ί Grid β€Ί Interconnection queues β€Ί South Dakota

OCTARY USA Β· INTERCONNECTION QUEUES

Withdrawn queue requests in South Dakota, MISO

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown9123.6 GW
Active in queue4,841 MW18 requests
Agreement signed100 MW2 requests
Withdrawn9123.6 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

91 requests Β· page 1 of 2
ProjectCapacityStatusLocationRegionQueuedOnline
Onshore wind project G705, Hand County
Onshore wind
2,000 MWWithdrawn / abandoned Hand, SDMISO Nov 2006target 2009
Onshore wind project G703, Hand County
Onshore wind
1,500 MWWithdrawn / abandoned Hand, SDMISO Nov 2006target 2007
Onshore wind project G704, Hand County
Onshore wind
1,500 MWWithdrawn / abandoned Hand, SDMISO Nov 2006target 2007
Onshore wind project G884, Roberts County
Onshore wind
1,500 MWWithdrawn / abandoned Roberts, SDMISO Oct 2007target 2011
Onshore wind project G731, Jerauld County
Onshore wind
750 MWWithdrawn / abandoned Jerauld, SDMISO Jan 2007target 2007
Other project G118, Grant County
Other
650 MWWithdrawn / abandoned Grant, SDMISO Aug 2001target 2005
Coal project G392, Grant County
Coal
600 MWWithdrawn / abandoned Grant, SDMISO Feb 2004target 2007
Onshore wind project H095, Roberts County
Onshore wind
550 MWWithdrawn / abandoned Roberts, SDMISO Aug 2008target 2010
Onshore wind project J4135, Grant County
Onshore wind
450 MWWithdrawn / abandoned Grant, SDMISO Oct 2025target 2030
Gas project J4032, Deuel County
Gas
442 MWWithdrawn / abandoned Deuel, SDMISO May 2025target 2030
Onshore wind project J1621, Mcpherson County
Onshore wind
400 MWWithdrawn / abandoned Mcpherson, SDMISO Jun 2020target 2023
Onshore wind project J744, Lincoln County
Onshore wind
400 MWWithdrawn / abandoned Lincoln, SDMISO Nov 2016target 2020
Onshore wind project J773, Codington County
Onshore wind
400 MWWithdrawn / abandoned Codington, SDMISO Nov 2016target 2019
Onshore wind project J151, Moody County
Onshore wind
350 MWWithdrawn / abandoned Moody, SDMISO Jun 2010target 2011
Onshore wind project J3279, Day County
Onshore wind
300 MWWithdrawn / abandoned Day, SDMISO Apr 2024target 2028
Onshore wind project J597, Deuel County
Onshore wind
300 MWWithdrawn / abandoned Deuel, SDMISO May 2016target 2016
Onshore wind project G982, Roberts County
Onshore wind
300 MWWithdrawn / abandoned Roberts, SDMISO Mar 2008target 2009
Battery storage project J4136, Grant County
Battery storage
250 MWWithdrawn / abandoned Grant, SDMISO Oct 2025target 2030
Onshore wind project G699, Roberts County
Onshore wind
250 MWWithdrawn / abandoned Roberts, SDMISO Nov 2006target 2008
Onshore wind project G939, Grant County
Onshore wind
250 MWWithdrawn / abandoned Grant, SDMISO Sep 2011
Onshore wind project G804, Deuel County
Onshore wind
250 MWWithdrawn / abandoned Deuel, SDMISO May 2007target 2009
Onshore wind project G722, Grant County
Onshore wind
250 MWWithdrawn / abandoned Grant, SDMISO Dec 2006target 2012
Battery storage project J3824, Roberts County
Battery storage
250 MWWithdrawn / abandoned Roberts, SDMISO Apr 2024target 2028
Solar project J3862, Deuel County
Solar
250 MWWithdrawn / abandoned Deuel, SDMISO Dec 2024target 2028
Onshore wind project J1989, Brown County
Onshore wind
250 MWWithdrawn / abandoned Brown, SDMISO Aug 2021target 2025
Onshore wind project G764, Minnehaha County
Onshore wind
242 MWWithdrawn / abandoned Minnehaha, SDMISO Mar 2007target 2013
Gas project G765, Brookings County
Gas
240 MWWithdrawn / abandoned Brookings, SDMISO Feb 2011target 2010
Onshore wind project J638, Deuel County
Onshore wind
204 MWWithdrawn / abandoned Deuel, SDMISO May 2016target 2019
Onshore wind project J266, Roberts County
Onshore wind
200 MWWithdrawn / abandoned Roberts, SDMISO Nov 2012target 2014
Onshore wind project H016, Minnehaha County
Onshore wind
200 MWWithdrawn / abandoned Minnehaha, SDMISO Apr 2008
Onshore wind project H025, Minnehaha County
Onshore wind
200 MWWithdrawn / abandoned Minnehaha, SDMISO Apr 2011target 2011
Onshore wind project J1594, Clark County
Onshore wind
200 MWWithdrawn / abandoned Clark, SDMISO Jun 2020target 2023
Onshore wind project J2338, Mcpherson County
Onshore wind
200 MWWithdrawn / abandoned Mcpherson, SDMISO Sep 2022target 2027
Onshore wind project J133, Codington County
Onshore wind
200 MWWithdrawn / abandoned Codington, SDMISO May 2010target 2013
Onshore wind project J933, Day County
Onshore wind
200 MWWithdrawn / abandoned Day, SDMISO Jun 2017target 2021
Onshore wind project J721, Codington County
Onshore wind
200 MWWithdrawn / abandoned Codington, SDMISO Oct 2016target 2019
Onshore wind project J2333, Mcpherson County
Onshore wind
200 MWWithdrawn / abandoned Mcpherson, SDMISO Sep 2022target 2027
Onshore wind project J629, Deuel County
Onshore wind
200 MWWithdrawn / abandoned Deuel, SDMISO May 2016target 2019
Onshore wind project J747, Deuel County
Onshore wind
200 MWWithdrawn / abandoned Deuel, SDMISO Nov 2016target 2017
Onshore wind project J458, Clark County
Onshore wind
200 MWWithdrawn / abandoned Clark, SDMISO May 2015target 2019
Onshore wind project J774, Codington County
Onshore wind
200 MWWithdrawn / abandoned Codington, SDMISO Nov 2016target 2019
Onshore wind project J630, Deuel County
Onshore wind
200 MWWithdrawn / abandoned Deuel, SDMISO May 2016target 2019
Onshore wind project J941, Grant County
Onshore wind
200 MWWithdrawn / abandoned Grant, SDMISO Jun 2017target 2020
Onshore wind project J599, Walworth County
Onshore wind
200 MWWithdrawn / abandoned Walworth, SDMISO May 2016target 2018
Onshore wind project J459, Grant County
Onshore wind
200 MWWithdrawn / abandoned Grant, SDMISO May 2015target 2017
Onshore wind project J189, Minnehaha County
Onshore wind
200 MWWithdrawn / abandoned Minnehaha, SDMISO Dec 2010target 2012
Onshore wind project G776, Brookings County
Onshore wind
200 MWWithdrawn / abandoned Brookings, SDMISO Mar 2007target 2010
Onshore wind project J775, Codington County
Onshore wind
200 MWWithdrawn / abandoned Codington, SDMISO Nov 2016target 2019
Onshore wind project J080, Brookings County
Onshore wind
200 MWWithdrawn / abandoned Brookings, SDMISO Oct 2009target 2011
Onshore wind project J1521, Day County
Onshore wind
200 MWWithdrawn / abandoned Day, SDMISO Jun 2020target 2022
Page 1 of 2

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)