πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί South Dakota

ONSHORE WIND Β· MISO

Onshore wind project J459, Grant County

Onshore wind project J459, Grant County is a 200 MW onshore wind request withdrawn in the MISO interconnection queue, in Grant County, South Dakota.

Queue statusWithdrawn / abandoned
  1. PlanningQueued May 2015 (completed)
  2. Withdrawn / abandonedOct 2018 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
J459
Grid region
MISO (Midcontinent)
Connection point (POI)
Big Stone Brookings 345kV
Location
Grant County, South Dakota
Technology
Wind: 200 MW
Total requested
200 MW
Study phase
GIA
Queue status
Withdrawn
Entered queue
18 May 2015
Proposed online date
September 2017
Withdrawn
October 2018

Location

Marker shows the centre of Grant County; the queue data does not give exact sites.

Power plants in South Dakota Β· Transmission lines in South Dakota

Other requests in Grant County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem