ONSHORE WIND Β· MISO

Onshore wind project G939, Grant County

Onshore wind project G939, Grant County is a 250 MW onshore wind request withdrawn in the MISO interconnection queue, in Grant County, South Dakota.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Sep 2011 (completed)
  2. Withdrawn / abandonedJan 2015 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
G939
Grid region
MISO (Midcontinent)
Connection point (POI)
OTP Big Stone 230 kV Substation
Location
Grant County, South Dakota
Technology
Wind: 250 MW
Total requested
250 MW
Study phase
SPA - SIS
Queue status
Withdrawn
Entered queue
26 September 2011
Withdrawn
January 2015

Location

Marker shows the centre of Grant County; the queue data does not give exact sites.

Power plants in South Dakota Β· Transmission lines in South Dakota

Other requests in Grant County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem