United States β€Ί Grid β€Ί Interconnection queues β€Ί South Dakota

ONSHORE WIND Β· WEST

Onshore wind project GI-1310, Grant County

Onshore wind project GI-1310, Grant County is a 201 MW onshore wind request withdrawn in the West interconnection queue, in Grant County, South Dakota, connecting to WAPA/BEPC/HCPD Integrated System.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Nov 2013 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
GI-1310
Grid region
West (non-ISO utilities)
Utility / transmission owner
WAPA/BEPC/HCPD Integrated System
Connection point (POI)
Summit 115kV
Location
Grant County, South Dakota
Technology
Wind: 201 MW
Total requested
201 MW
Service type
NRIS and ERIS
Study phase
IP
Queue status
Withdrawn
Entered queue
18 November 2013
Proposed online date
December 2017

Location

Marker shows the centre of Grant County; the queue data does not give exact sites.