ONSHORE WIND Β· MISO

Onshore wind project G764, Minnehaha County

Onshore wind project G764, Minnehaha County is a 242 MW onshore wind request withdrawn in the MISO interconnection queue, in Minnehaha County, South Dakota.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Mar 2007 (completed)
  2. Withdrawn / abandonedJul 2012 (project stopped here)
  3. ConsentedJul 2012 (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
G764
Grid region
MISO (Midcontinent)
Connection point (POI)
Anson 115 kV station
Location
Minnehaha County, South Dakota
Technology
Wind: 242 MW
Total requested
242 MW
Study phase
SPA - SIS
Queue status
Withdrawn
Entered queue
15 March 2007
Agreement signed
3 July 2012
Proposed online date
December 2013
Withdrawn
July 2012

Location

Marker shows the centre of Minnehaha County; the queue data does not give exact sites.

Power plants in South Dakota Β· Transmission lines in South Dakota

Other requests in Minnehaha County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem