United States β€Ί Grid β€Ί Interconnection queues β€Ί South Dakota

ONSHORE WIND Β· MISO

Onshore wind project G705, Hand County

Onshore wind project G705, Hand County is a 2,000 MW onshore wind request withdrawn in the MISO interconnection queue, in Hand County, South Dakota.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Nov 2006 (completed)
  2. Withdrawn / abandonedApr 2012 (project stopped here)
  3. ConsentedApr 2012 (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
G705
Grid region
MISO (Midcontinent)
Connection point (POI)
Sioux Falls or Brookings Sub
Location
Hand County, South Dakota
Technology
Wind: 2,000 MW
Total requested
2,000 MW
Study phase
SPA - SIS
Queue status
Withdrawn
Entered queue
10 November 2006
Agreement signed
23 April 2012
Proposed online date
October 2009
Withdrawn
April 2012

Location

Marker shows the centre of Hand County; the queue data does not give exact sites.

Power plants in South Dakota Β· Transmission lines in South Dakota

Other requests in Hand County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem