United States β€Ί Grid β€Ί Interconnection queues β€Ί South Dakota

ONSHORE WIND Β· WEST

Onshore wind project GI-0710, Hand County

Onshore wind project GI-0710, Hand County is a 100 MW onshore wind request withdrawn in the West interconnection queue, in Hand County, South Dakota, connecting to WAPA/BEPC/HCPD Integrated System.

Queue statusWithdrawn / abandoned
  1. PlanningQueued May 2007 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
GI-0710
Grid region
West (non-ISO utilities)
Utility / transmission owner
WAPA/BEPC/HCPD Integrated System
Connection point (POI)
Ft. Thompson - Huron 230kV
Location
Hand County, South Dakota
Technology
Wind: 100 MW
Total requested
100 MW
Service type
NRIS and ERIS
Study phase
IAP
Queue status
Withdrawn
Entered queue
24 May 2007
Proposed online date
December 2009

Location

Marker shows the centre of Hand County; the queue data does not give exact sites.

Power plants in South Dakota Β· Transmission lines in South Dakota

Other requests in Hand County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem