Onshore wind project GEN-2017-094, Hand County

Onshore wind project GEN-2017-094, Hand County is a 200 MW onshore wind request built and operating in the SPP interconnection queue, in Hand County, South Dakota, connecting to WAPA.

Queue statusOperating
  1. PlanningQueued May 2017 (completed)
  2. Consented (completed)
  3. Construction (completed)
  4. OperatingNov 2023 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
GEN-2017-094
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
WAPA
Connection point (POI)
Fort Thompson-Huron 230 kV
Location
Hand County, South Dakota
Technology
Wind: 200 MW
Total requested
200 MW
Service type
Energy only (ERIS)
Study phase
IA FULLY EXECUTED/COMMERCIAL OPERATION
Queue status
Operational
Entered queue
24 May 2017
Proposed online date
November 2023
Came online
November 2023

Location

Marker shows the centre of Hand County; the queue data does not give exact sites.

Power plants in South Dakota · Transmission lines in South Dakota

Other requests in Hand County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem